August 2022 |
September 2022 |
|
·
Piling work at PST; ·
Piling work at STB ; ·
ELS works at IW & PST; ·
Zone 3 Diversion works: a.
Temp. Gravity thickening
tank – Pipe laying and E&M installation work; b.
Temp. Sludge Holding Tank
– Pipe laying and E&M installation work; c.
Temp. Water heater house –
Pipe laying and E&M installation work; d.
Temp. Primary Sludge
Pumping Station – RC work; e.
Temp. Digested sludge pump
/ Supernatant Pumping – RC Work; f.
Digested Sludge Pumping
Station house – Pipe laying and E&M installation work; g.
Pipe laying for Zone 3 diversion; ·
Demolition of Sludge Holding Tank no. 1; ·
Backfilling work at
Sludge Holding Tank no. 3 & 4; ·
Superstructure works at CLP substation; ·
Installation of MIC unit
at MIC office; ·
Backfill work at A.
Tank 6-8; ·
Construction of RC chamber
at Zone 2B; ·
Disposal of Pond
Sediment excavated from PST; and · Disposal
of construction waste as indicated in Appendix F. |
· Piling work at PST; · Piling work at STB; · ELS works at IW & PST; · Zone 3 Diversion works: a.
Temp. Gravity thickening tank – Pipe laying and
E&M installation work; b.
Temp. Sludge Holding Tank – Pipe laying and
E&M installation work; c.
Temp. Water heater house – Pipe laying and
E&M installation work; d.
Temp. Primary Sludge Pumping Station – RC work; e.
Temp. Digested sludge pump / Supernatant Pumping
– RC Work; f.
Digested Sludge Pumping Station house – Pipe
laying and E&M installation work; g.
Pipe laying for Zone 3 diversion; · Demolition of Sludge Holding Tank no. 1; · Installation of 813mm pipe pile at south of AGS; · Backfilling work at Sludge
Holding Tank no. 1 & 3; · Superstructure works at CLP substation; · Installation of MIC
unit at MIC office; · Backfill work at A. Tank 6-8; · Construction of RC chamber at Zone
2B; · Disposal of Pond Sediment
excavated from PST-Zone E;
and · Disposal of construction waste as
indicated in Appendix F. |
· Piling work at STB; · ELS works and RC structure works at IW & PST; · Zone 3 Diversion works: a.
Temp. Gravity
thickening tank – Pipe laying and E&M installation work; b.
Temp. Sludge Holding
Tank – Pipe laying and E&M installation work; c.
Temp. Water heater
house – Pipe laying and E&M installation work; d.
Temp. Primary Sludge
Pumping Station – Pipe laying and E&M installation work; e.
Temp. Digested sludge
pump / Supernatant Pumping – Pipe laying and E&M installation work; f.
Digested Sludge
Pumping Station house – Pipe laying and E&M installation work; · Installation of sheet piles at DS; · Installation of 813mm pipe pile at south of AGS; · Backfilling work at
Sludge Holding Tank no. 1 & 3; · Superstructure works at CLP substation; · Installation of MIC unit at MIC office; · Backfill work at
A. Tank 5-8; · E&M
installation work for at Zone 2B chamber; · Pipe laying for Zone 2B; and · Disposal of construction waste as
indicated in Appendix F. |