May 2022 |
June 2022 |
|
· Demolition of FST no. 5-6 by excavator
mounted crusher; · Demolition of Auxiliary Pumping
Station (above ground); · Pre-drill work at A. tank by 1 rig; · Pre-drill work at Air Flotation
Thickener and Sludge Digestion Tank by 3 rigs; · Installation of sheet pile at IW
& PST; · Piling work at PST; · Drilling and installation of
dewatering well and observation well at IW & PST; · ELS works at IW & PST; · ELS work at Zone 2B; · Pipe laying for Zone 3 diversion; · Zone 3 Diversion works: a. Temp. Gravity thickening tank – Pipe
laying and E&M installation work; b. Temp. Sludge Holding Tank – Pipe
laying and E&M installation work; c. Temp. Water heater house – Pipe
laying and E&M installation work; d. Temp. Primary Sludge Pumping Station
– Sheet piling work; e. Temp. Digested sludge pump – ELS
Work; f. Digested Sludge Pumping Station
house – Pipe laying and E&M installation work; · Demolition works at Sha Tin
Treatment Plant; · Demolition of Sludge Holding Tank
no. 3 & 4; · Foundation works at CLP substation; · Foundation works at MIC office; · Env. Drill holes inside Air
Flotation Thickener; and · Disposal of construction waste as
indicated in Appendix F. |
· Pre-drill work at A.tank by 1 rig; · Pre-drill work at Air Flotation
Thickener and Sludge Digestion Tank by 3 rigs; · Installation of sheet pile at IW
& PST; · Piling work at PST; · Drilling and installation of
dewatering well and observation well at IW & PST; · ELS works at IW & PST; · Pipe laying for Zone 3 diversion; · Zone 3 Diversion works: a.
Temp.
Gravity thickening tank – Pipe laying and E&M installation work; b.
Temp.
Sludge Holding Tank – Pipe laying and E&M installation work; c.
Temp.
Water heater house – Pipe laying and E&M installation work; d.
Temp.
Primary Sludge Pumping Station – ELS work; e.
Temp.
Digested sludge pump / Supernatant Pumping – ELS Work; f.
Ferrie Chloride and Chemical Dosing System – R.C.
works; g.
Digested
Sludge Pumping Station house – Pipe laying and E&M installation work; · Demolition of Sludge Holding Tank
no. 3; · Foundation works at CLP substation; · Installation of MIC unit at MIC
office; · Backfill work at FST no. 5-8; · ELS works at Zone 2B; and · Disposal of construction waste as
indicated in Appendix F. |
· Sludge Digestion Tank by 1 rigs; · Installation of sheet pile at IW
& PST; · Piling work at PST; · Piling work at Transformer House; · Drilling and installation of
dewatering well and observation well at IW & PST; · ELS works at IW & PST; · Pipe laying for Zone 3 diversion; · Zone 3 Diversion works: a.
Temp.
Gravity thickening tank – Pipe laying and E&M installation work; b.
Temp.
Sludge Holding Tank – Pipe laying and E&M installation work; c.
Temp.
Water heater house – Pipe laying and E&M installation work; d.
Temp.
Primary Sludge Pumping Station – ELS work; e.
Temp.
Digested sludge pump / Supernatant Pumping – ELS Work; f.
Ferrie Chloride and Chemical Dosing System – R.C.
works; g.
Digested
Sludge Pumping Station house – Pipe laying and E&M installation work; · Demolition of Sludge Holding Tank
no. 1, 3 & 4; · Foundation works at CLP substation; · Installation of MIC unit at MIC
office; · Backfill work at FST no. 5-8; · Backfill work at A. Tank 6-8; · Construction of RC chamber at Zone
2B; · Disposal of Pond Sediment excavated
from PST; and · Disposal of construction waste as
indicated in Appendix F. |