Table
5.1 – Observations and Recommendations of Site Audit
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Air
Quality |
6 Apr 2022 |
Recommendation 1: The Contractor is recommended to
provide water spraying to prevent dust emission for access road at FST Area
(Portion 1 -YLSTW). |
6 Apr 2022 |
12 Apr 2022 |
Reminder 1: The Contractor
is reminded to provide water spraying for dust suppression at haul roads
(Portion 1 - YLSTW). |
12 Apr 2022 |
|
29 Jun 2022 |
Reminder 1: The Contractor is reminded to
provide water spraying for dust suppression at loading/unloading area and
haul roads (Portion 1 - YLSTW). |
NA |
|
Noise |
NA |
||
Water
Quality |
1 Jun 2022 |
Reminder 1: The Contractor is reminded to
provide sandbags to prevent runoff into the storm drain (Portion 1 - YLSTW). |
NA |
10 Jun 2022 |
Reminder 1: The Contractor
is reminded to provide sandbags to prevent silty runoff into the storm drain
(Portion 1 - YLSTW). |
NA |
|
Chemical
and Waste Management |
20 Apr 2022 |
Reminder 1: The Contractor is reminded to clean
up the oil stain on road with chemical absorbent pad and treat it as chemical
waste for disposal (Portion 1 - YLSTW). |
20 Apr 2022 |
25 May 2022 |
Reminder 1: The Contractor
is reminded to clean up the oil stain on road with chemical absorbent pad and
treat it as chemical waste for disposal (Portion 1 - YLSTW). |
26 May 2022 |
|
Land
Contamination |
NA |
||
Ecological
Impact |
4 May 2022 |
Reminder 1: The Contractor
is reminded to maintain and reinstate the bird curtains at the east site
boundary (Portion 1 - YLSTW). |
NA |
18 May 2022 |
Reminder 1: The Contractor is reminded to
maintain and reinstate the bird curtains at the northern and eastern site
boundary (Portion 1 - YLSTW). |
NA |
|
25 May 2022 |
Reminder 1: The Contractor
is reminded to maintain and reinstate the bird curtains at the eastern & northern
site boundary (Portion 1 - YLSTW). |
NA |
|
1 Jun 2022 |
Reminder 1: The Contractor is reminded to
maintain and reinstate the bird curtains at the eastern & northern site
boundary (Portion 1 - YLSTW). |
NA |
|
22 Jun 2022 |
Reminder 1: The Contractor
is reminded to maintain and reinstate the bird curtains at the eastern and
northern site boundary (Portion 1 - YLSTW). |
NA |
|
Landscape
and Visual Impact |
27 Apr 2022 |
Reminder 1 (Landscape & Visual
Impact): Please keep adjacent ground of trees
free of construction materials (Portion 1 - YLSTW). |
27 Apr 2022 |
18 May 2022 |
Recommendation
1 (Landscape & Visual Impact): All trees shall
be checked to ensure no construction materials or cables attached to them
(Portion 1 - YLSTW). |
19 May 2022 |
|
10 Jun 2022 |
Recommendation 1 (Landscape &
Visual Impact): Please provide maintenance check
after rainstorms for possible broken branches or other possible damages to
trees (Portion 1 - YLSTW). |
NA |
|
Permit
/ Licenses |
NA |
||
Others |
NA |