Table 1.2 – Main Construction Works Carried out in the Reporting Period

July 2021

August 2021

September 2021

·  Pre-drill work at Primary Sedimentation Tanks (PST) by 3 drill rigs;

·  Site formation works at Primary Sedimentation Tanks (PST) no. 7 & 8;

·  Breaking of Primary Sedimentation Tanks (PST) no. 8;

·  Sheet pile installation works for Zone 2A diversion;

·  Driven H-pile at Inlet Works (IW) stage 1, 2 and Primary Sedimentation Tanks by 3 rigs;

·  Demolition of workshop and changing room by crusher and breaker;

·  Demolition of carparks;

·  Trial pit for Zone 2B & 3 diversion;

·  Removal of sludge from sludge holding tanks; and

·  Overhaul work at Final Sedimentation Tanks (FST).

(FST).

·  Pre-drill work at Primary Sedimentation Tanks (PST) by 1 drill rig;

·  Pre-drill work at CLP by 1 drill rig;

·  Temporary backfilling at PST no. 7 & 8;

·  Installation of DN1200 pipe and construction manhole for Zone 1 diversion;

·  Demolition of workshop and carpark by crusher and breaker;

·  Trial pit for Zone 2B & Zone 3;

·  Overhaul work at Final Sedimentation Tanks (FST); and

·  Site Investigation (SI) works for the Contamination Assessment Report (CAR) for Main Storeroom & Workshops and Mechanical Workshop.

·  Site formation works at PST no. 7 & 8;

·  Removal of existing pipes at PST no. 7 & 8;

·  Driven H-pile at IW stage 1 by 4 rigs;

·  Demolition of Workshop and Detritor 3C by crusher and breaker;

·  Trial pit for Zone 2A & 3 diversion; and

·  Removal of sludge at FST no. 7 & 8.