Table 28 Status
of submissions required under the EP
EP Condition (EP-565/2019) |
Submission Title |
Submission Status |
Condition
2.9 |
Construction
Phase Emergency Response Plan |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 2.11 |
Pre-construction Ardeid Night Roost Survey Report |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
EM&A
Manual Sec. 7.3.3 & 7.3.4 |
Baseline
Bird Survey Report |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 2.12 |
Noise Mitigation Measures Plan |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition
2.13 |
Proposal
for Minimization of Overspill Light to Ecological Sensitive Areas |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 2.14 |
Supplementary Contamination Assessment Plan |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition
2.14 |
Contamination
Assessment Report for Main Storeroom & Workshops |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for Mechanical
Workshop |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition
2.14 |
Contamination
Assessment Report for Waste Storage Area |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for SAS Thickener
House-1 |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition
2.14 |
Contamination
Assessment Report for SAS Thickener House-2 |
Certified
by ET Leader and verified by IEC on 31 May 2023 and submitted to EPD on 19
Jun 2023, to be finalised and made available for public inspection via the
dedicated website. |
Condition 2.15 |
Landscape and Visual Mitigation Plan |
Submitted to
EPD with ET certification and IEC verification, to be finalised and made
available for public inspection via the dedicated website. |
Condition
3.3 |
Baseline
Monitoring Report |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 3.4 |
Monthly EM&A Report (from April 2021 to July
2023) |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition
3.5 |
Quarterly
EM&A Report (from April 2021 to June 2023) |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
Condition 4.2 |
Environmental Monitoring Data from April 2021 to July
2023 |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |