Table 1.2 – Main Construction Works Carried out in the Reporting Period

April 2023

May 2023

June 2023

·   ELS works and RC structure works at IW & PST;

·   Installation of 813mm pipe pile at North & West of AGS;

·   ABWF and E&M works at CLP substation;

·   Ground investigation at SDB;

·   Sheet piling installation around Sludge digester no. 1 – 3;

·   Installation of sheet pile at TTS;

·   Installation of sheet pile at STB;

·   Excavation of trench for laying power cables and construction of cable draw pits near entrance of YLSTP;

·   Demolition of Admin. Building;

·   Installation of King Post at AGS;

·   Laying 1200mm outfall pipe for temp. diversion;

·   Installation of sheet pile at UC5; and

·   Disposal of construction waste as indicated in Appendix F.

·   ABWF and E&M works at CLP substation;

·   ELS works and RC structure works at IW & PST;

·   Installation of 813mm pipe pile at North & West of AGS;

·   Ground investigation at SDB;

·   Sheet piling installation around Sludge digester no. 1 – 3;

·   Installation of sheet pile at TTS:

·   Installation of sheet pile at STB;

·   Installation of sheet pile at UC5;

·   Laying cable ducts and construction of cable draw pits near entrance of YLSTP;

·   Installation of King Post at AGS;

·   Laying 1200mm outfall pipe for temp. diversion; and

·   Disposal of construction waste as indicated in Appendix F.

·   ABWF and E&M works at CLP substation;

·   ELS works and RC structure works at IW & PST;

·   Installation of 813mm pipe pile at North & West of AGS;

·   Ground investigation at SDB & TTS;

·   Sheet piling installation around Sludge digester no. 1 – 3;

·   Installation of sheet pile at TTS:

·   Installation of sheet pile at STB;

·   Installation of sheet pile at UC5;

·   Laying cable ducts and construction of cable draw pits near entrance of YLSTP;

·   Installation of King Post at AGS;

·   Laying 1200mm outfall pipe for temp. diversion;

·   Removal of surcharge including concrete blocks and filled soil at Biogas Holder no. 1;

·   ELS and construction of UC no.5;

·   Laying cable ducts and construction of cable draw pits near entrance of YLSTP;

·   Breaking and removal of RAS (below ground); and

·   Disposal of construction waste as indicated in Appendix F.