11.1
Construction Programme for the Next Three Months
·
Ground investigation at SDB,
AGS & TTS.
·
Ground investigation and
footing construction works at Walkway (Portion 5)
·
ABWF work and fixing GRC panel
at CLP Substation
·
ELS work and RC structure at IW
& PST
·
Installation of King Post at
AGS
·
Installation of 813mm pipe pile
at North near West of AGS
·
Installation of observation
wells and dewatering well at AGS
·
Erection temp. loading platform
at AGS
·
ELS work at AGS
·
Demolition of underground
structure at Aeration Tank no. 5-8
·
Installation of Sheet pile at
TTS
·
Installation of King post at
TTS
·
Installation of observation
wells and dewatering well at TTS
·
Erection temp. loading platform
at TTS
·
ELS work at TTS
·
Demolition of Mixed Liquor
Distribution & sludge Draw-off Chamber at FST no. 5-8
·
Demolition of underground
structure at pump room of AFT
·
Driven pile works at STB
(17nos.)
·
Installation of sheet pile at
STB
·
ELS work at STB
·
Installation of observation
wells and dewatering well at STB
·
ELS and construction of UC no.5
·
Sheet piling work around Sludge
Digester no. 1-3
·
ELS work at Sludge Digester no.
1-3
·
Installation of observation
wells and dewatering well at Sludge Digester no. 1-3
·
Installation of sheet pile at
Biogas Holder no. 1
·
ELS work at Biogas Holder no. 1
·
Driven pile works at UC
(24nos.) near SDB
· Construction of temp. haul road in front of central Control Room
11.2
Key Issues for the Coming Month
Potential environmental
impacts arising from the above construction activities are mainly associated with
construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3
Monitoring Schedules for the next three months
The tentative schedule for
environmental monitoring in the next three months is provided in Appendix E.