12.
CONCLUSION AND
RECOMMENDATION
12.1.1
1-hour TSP impact monitoring was carried out in the reporting month. No
Action / Limit Level exceedance at AM1 and AM2 was recorded during the period.
12.1.2
Construction noise monitoring was carried out in the reporting month. No
Action / Limit Level exceedance at CM1, CM2 and CM3 was recorded during the
period.
12.1.3
No Action and Limit Level exceedance was recorded for water quality at
M1, M2 and M3 in the reporting month.
12.1.4
Ardeid night roost monitoring was carried out in the reporting month.
Two active ardeid night roost areas (ANR1 and ANR2) were observed within the
Survey Area. These roosts were located at the mangrove strips in the east and
northeast portions of the Project boundary. No Action / Limit Level exceedance
at NMS1 and NMS2 was recorded during the period.
12.1.5
Ecological bird monitoring was carried out in the reporting month. No
Action / Limit exceedances was recorded for the ecological monitoring of birds
during the period.
12.1.6
Four environmental site inspections were carried out in the reporting
month. Recommendations on mitigation measures for Permit/ Licenses were given
to the Contractor for remediating the deficiencies identified during the site
inspections.
12.1.7
Four landscape and visual site audits were carried out in the reporting
month. Recommendations on mitigation measures for Permit/ Licenses were given
to the Contractor for remediating the deficiencies identified during the site
inspections.
12.1.8
No environmental complaint, notification of summons and successful
prosecution was recorded in the reporting month.
12.2
Comment and Recommendations
12.2.1
The recommended environmental mitigation measures, as proposed in the
EIA report and EM&A Manual shall be effectively implemented to minimize the
potential environmental impacts from the Project. The EM&A programme would
effectively monitor the environmental impacts generated from the construction
activities and ensure the proper implementation of mitigation measures.
12.2.2
According to the environmental site inspections performed in the
reporting month, the following recommendations were provided:
Air Quality Impact
·
No specific observation was identified in the reporting month.
Construction Noise Impact
·
The Contractor is reminded to maintain and reinstate the silentup at northern and western site boundary.
Water Quality Impact
·
No specific observation was identified in the reporting month.
Chemical Waste and
Construction Waste Management
·
No specific observation was identified in the reporting month.
Land Contamination
·
No specific observation was identified in the reporting month.
Ecological Impact
·
No specific observation was identified in the reporting month.
Landscape and Visual Impact
·
No specific observation was identified in the reporting month.
Hazard to Life
·
No specific observation was identified in the reporting month.
Permit/ Licenses
·
No specific observation was identified in the reporting month.