Table 2     Main Construction Works carried out in the Reporting Period
| 
    July 2023  | 
   
    August 2023  | 
   
    September 2023  | 
  
| 
   ·  Ground investigation at SDB & TTS ·  Laying cable ducts and construction of
  cable draw pits near entrance of YLSTW ·  ABWF and E&M works at CLP
  substation ·  ELS works and RC structure works at IW
  & PST ·  Installation of 813mm pipe pile at
  North of AGS ·  Installation of King Post at AGS ·  Breaking and removal of RAS (below ground) ·  Installation of observation wells and
  dewatering well at AGS ·  Demolition of Mixed Liquor
  Distribution & sludge Draw-off Chamber at FST no. 5-8 ·  Installation of sheet pile at TTS ·  Installation of King post at TTS ·  Installation of observation wells and
  dewatering well at TTS ·  Installation of sheet pile at STB ·  Demolition of underground structure at
  pump room of AFT ·  Installation of sheet pile at UC5 ·  ELS works at UC5 ·  Sheet piling installation around
  Sludge digester no. 1 – 3 ·  Installation of sheet pile at Biogas Holder
  no. 1 ·  Construction of temporary 200m3 sludge
  holding tanks, and ·  Disposal of construction waste as
  indicated in Appendix F.  | 
  
   ·  Ground investigation at SDB ·  Laying cable ducts and construction of
  cable draw pits near entrance of YLSTW ·  ABWF and E&M works at CLP
  substation ·  ELS works and RC structure works at IW
  & PST ·  Installation of 813mm pipe pile at
  North of AGS ·  Installation of King Post at AGS ·  Installation of observation wells and
  dewatering well at AGS ·  Installation of sheet pile at TTS ·  Installation of King post at TTS ·  Installation of observation wells and
  dewatering well at TTS ·  Installation of sheet pile at STB ·  Demolition of underground structure at
  pump room of AFT ·  ELS works at UC5 ·  Sheet piling installation around
  Sludge digester no. 1 – 3 ·  Installation of sheet pile at Biogas
  Holder no. 1 ·  Construction of temporary 200m3 sludge
  holding tanks ·  Construction of temp. haul road in
  front of central Control Room, and ·  Disposal of construction waste as
  indicated in Appendix F.  | 
  
   ·  Ground investigation at SDB, AGS &
  TTS ·  Laying cable ducts and construction of
  cable draw pits near entrance of YLSTW ·  ABWF and E&M works at CLP
  substation ·  ELS works and RC structure works at IW
  & PST ·  Installation of 813mm pipe pile at
  North of AGS ·  Installation of King Post at AGS ·  Breaking and removal of RAS (below
  ground) ·  Installation of observation wells and
  dewatering well at AGS ·  Demolition of Mixed Liquor
  Distribution & sludge Draw-off Chamber at FST no. 5-8 ·  Installation of sheet pile at TTS ·  Installation of King post at TTS ·  Installation of observation wells and
  dewatering well at TTS ·  Installation of sheet pile at STB ·  Demolition of underground structure at
  pump room of AFT ·  Installation of sheet pile at UC5 ·  ELS works at UC5 ·  Sheet piling installation around
  Sludge digester no. 1 – 3 ·  Installation of sheet pile at Biogas
  Holder no. 1 ·  Construction of temporary 200m3 sludge
  holding tanks, and ·  Disposal of construction waste as
  indicated in Appendix F.  |