Table 2 Main Construction Works carried out in the Reporting Period
July 2023 |
August 2023 |
September 2023 |
· Ground investigation at SDB & TTS · Laying cable ducts and construction of
cable draw pits near entrance of YLSTW · ABWF and E&M works at CLP
substation · ELS works and RC structure works at IW
& PST · Installation of 813mm pipe pile at
North of AGS · Installation of King Post at AGS · Breaking and removal of RAS (below ground) · Installation of observation wells and
dewatering well at AGS · Demolition of Mixed Liquor
Distribution & sludge Draw-off Chamber at FST no. 5-8 · Installation of sheet pile at TTS · Installation of King post at TTS · Installation of observation wells and
dewatering well at TTS · Installation of sheet pile at STB · Demolition of underground structure at
pump room of AFT · Installation of sheet pile at UC5 · ELS works at UC5 · Sheet piling installation around
Sludge digester no. 1 – 3 · Installation of sheet pile at Biogas Holder
no. 1 · Construction of temporary 200m3 sludge
holding tanks, and · Disposal of construction waste as
indicated in Appendix F. |
· Ground investigation at SDB · Laying cable ducts and construction of
cable draw pits near entrance of YLSTW · ABWF and E&M works at CLP
substation · ELS works and RC structure works at IW
& PST · Installation of 813mm pipe pile at
North of AGS · Installation of King Post at AGS · Installation of observation wells and
dewatering well at AGS · Installation of sheet pile at TTS · Installation of King post at TTS · Installation of observation wells and
dewatering well at TTS · Installation of sheet pile at STB · Demolition of underground structure at
pump room of AFT · ELS works at UC5 · Sheet piling installation around
Sludge digester no. 1 – 3 · Installation of sheet pile at Biogas
Holder no. 1 · Construction of temporary 200m3 sludge
holding tanks · Construction of temp. haul road in
front of central Control Room, and · Disposal of construction waste as
indicated in Appendix F. |
· Ground investigation at SDB, AGS &
TTS · Laying cable ducts and construction of
cable draw pits near entrance of YLSTW · ABWF and E&M works at CLP
substation · ELS works and RC structure works at IW
& PST · Installation of 813mm pipe pile at
North of AGS · Installation of King Post at AGS · Breaking and removal of RAS (below
ground) · Installation of observation wells and
dewatering well at AGS · Demolition of Mixed Liquor
Distribution & sludge Draw-off Chamber at FST no. 5-8 · Installation of sheet pile at TTS · Installation of King post at TTS · Installation of observation wells and
dewatering well at TTS · Installation of sheet pile at STB · Demolition of underground structure at
pump room of AFT · Installation of sheet pile at UC5 · ELS works at UC5 · Sheet piling installation around
Sludge digester no. 1 – 3 · Installation of sheet pile at Biogas
Holder no. 1 · Construction of temporary 200m3 sludge
holding tanks, and · Disposal of construction waste as
indicated in Appendix F. |