Table 28 Status of submissions required under the EP
EP Condition
(EP-565/2019) |
Submission Title |
Submission
Status |
Condition 2.9 |
Construction Phase
Emergency Response Plan |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.11 |
Pre-construction Ardeid Night Roost Survey Report |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
EM&A Manual Sec. 7.3.3
& 7.3.4 |
Baseline Bird Survey Report |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.12 |
Noise Mitigation Measures Plan |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.13 |
Proposal for Minimization
of Overspill Light to Ecological Sensitive Areas |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Supplementary Contamination Assessment Plan |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment
Report for Main Storeroom & Workshops |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for Mechanical
Workshop |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report
for Waste Storage Area |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for SAS Thickener
House-1 |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment
Report for SAS Thickener House-2 |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.15 |
Landscape and Visual Mitigation Plan |
Submitted to EPD with ET
certification and IEC verification, to be finalised and made available for
public inspection via the dedicated website. |
Condition 3.3 |
Baseline Monitoring Report |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 3.4 |
Monthly EM&A Report (from April 2021 to February
2024) |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 3.5 |
Quarterly EM&A Report
(from April 2021 to February 2024) |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 4.2 |
Environmental Monitoring Data from April 2021 to February
2024 |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |