Table 2 Main Construction Works carried out in the Reporting Period
April 2024 |
May 2024 |
June 2024 |
·
Piling at SDB ·
ABWF work, E&M works and fixing GRC panel at CLP Substation ·
ABWF and E&M works at PST ·
ABWF, E&M works and RC structure at IW ·
Erection temp. loading platform at AGS ·
ELS work at AGS ·
Erection temp. loading platform at TTS ·
ELS work at TTS ·
ELS work at STB ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Pipeworks for interim scheme ·
Disposal of construction waste as indicated in Appendix F.
|
·
Piling at SDB ·
ABWF work, E&M works and fixing GRC panel at CLP Substation ·
ABWF and E&M works at PST ·
ABWF, E&M works and RC structure at IW ·
•Erection temp. loading platform at AGS ·
ELS work at AGS ·
Erection temp. loading platform at TTS ·
ELS work at TTS ·
ELS work at STB ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Pipeworks for interim scheme ·
Disposal of construction waste as indicated in Appendix F.
|
·
Demolition at existing PST ·
E&M works and fixing GRC panel at CLP Substation ·
ABWF and E&M works at PST ·
ABWF, E&M work and RC structure at IW ·
ELS work at AGS ·
ELS work at TTS ·
ELS work at STB ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
ELS works at emergency bypass chamber ·
Disposal of construction waste as indicated in Appendix F. |