11.1
Construction Programme for the Next Three Months
·
Demolition
at existing PST
·
ABWF
work, E&M works and fixing GRC panel at CLP Substation
·
ABWF
and E&M works at PST
·
ABWF,
E&M work and RC structure at IW
·
ELS
work at AGS
·
ELS
work at TTS
·
RC
Structure at TTS
·
ELS
work at STB
·
RC
Structure at STB
·
ELS
work at Sludge Digester no. 1-3
·
E&M
work at Biogas Holder no. 1
·
ELS
works and pipeworks at emergency bypass chamber
11.2
Key Issues for the Coming Month
Potential environmental
impacts arising from the above construction activities are mainly associated with
construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3
Monitoring Schedules for the next three months
The tentative schedule for
environmental monitoring in the next three months is provided in Appendix E.