12.
CONCLUSION AND
RECOMMENDATION
12.1.2
Construction
noise monitoring was carried out in the reporting month. No Action / Limit
Level exceedance at CM1, CM2 and CM3 was recorded during the period.
12.1.3
No
Action and Limit Level exceedance was recorded for water quality at M1, M2 and
M3 in the reporting month.
12.1.4
Ardeid
night roost monitoring was carried out in the reporting month. Two active
ardeid night roost areas (ANR1 and ANR2) were observed within the Survey Area.
These roosts were located at the mangrove strips in the east and northeast
portions of the Project boundary. No Action / Limit Level exceedance at NMS1
and NMS2 was recorded during the period.
12.1.5
Ecological
bird monitoring was carried out in the reporting month. No Action / Limit
exceedance for the ecological monitoring of birds in the reporting month.
12.1.6
Four
environmental site inspections were carried out in the reporting month.
Recommendations on mitigation measures for air quality impact,
chemical waste
and construction waste
management and permit/ licenses
were given to the Contractor for
remediating the deficiencies identified during the site inspections.
12.1.7
Four
landscape and visual site audits were carried out in the reporting month. No recommendations
on mitigation measures were given to the Contractor for
remediating the deficiencies identified during the site inspections.
12.1.8
No
environmental complaint, notification of summons and successful prosecution was
recorded in the reporting month.
12.2
Comment and Recommendations
12.2.1
The
recommended environmental mitigation measures, as proposed in the EIA report
and EM&A Manual shall be effectively implemented to minimize the potential
environmental impacts from the Project. The EM&A programme
would effectively monitor the environmental impacts generated from the
construction activities and ensure the proper implementation of mitigation
measures.
12.2.2
According
to the environmental site inspections performed in the reporting month, the
following recommendations were provided:
Air Quality Impact
·
The contractor was
remaindered to increase watering for the haul road.
Construction Noise Impact
·
No
specific observation was identified in the reporting month.
Water Quality Impact
·
No
specific observation was identified in the reporting month.
Chemical Waste and Construction Waste
Management
·
The contractor was
reminded to clear the construction waste regularly.
Land Contamination
·
No
specific observation was identified in the reporting month.
Ecological Impact
·
No
specific observation was identified in the reporting month.
Landscape and Visual Impact
·
No
specific observation was identified in the reporting month.
Hazard to Life
·
No
specific observation was identified in the reporting month.
Permit/ Licenses
·
The contractor was
reminded to display NRMM label on the PME.
13.