Table 28 Status
of submissions required under the EP
EP Condition (EP-565/2019) |
Submission
Title |
Submission Status |
Condition 2.9 |
Construction Phase Emergency Response
Plan |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.11 |
Pre-construction Ardeid Night Roost Survey Report |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
EM&A Manual Sec. 7.3.3 & 7.3.4 |
Baseline Bird Survey Report |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.12 |
Noise Mitigation Measures Plan |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 2.13 |
Proposal for Minimization of Overspill
Light to Ecological Sensitive Areas |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Supplementary Contamination Assessment Plan |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 2.14 |
Contamination Assessment Report for
Main Storeroom & Workshops |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 2.14 |
Contamination Assessment Report for Mechanical Workshop |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 2.14 |
Contamination Assessment Report for
Waste Storage Area |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for SAS Thickener House-1 |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 2.14 |
Contamination Assessment Report for
SAS Thickener House-2 |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.15 |
Landscape and Visual Mitigation Plan |
Submitted to EPD with ET certification
and IEC verification, to be finalised and made available for public
inspection via the dedicated website. |
Condition 3.3 |
Baseline Monitoring Report |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 3.4 |
Monthly EM&A Report (from April 2021 to April 2024) |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |
Condition 3.5 |
Quarterly EM&A Report (from April
2021 to March 2024) |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 4.2 |
Environmental Monitoring Data from April 2021 to April 2024 |
Submitted to EPD with ET certification
and IEC verification, finalised and available for public inspection via the
dedicated website. |