11                FUTURE KEY ISSUES

11.1            Construction Programme for the Next Three Months

·       Piling at SDB

·       Demolition at existing PST

·       E&M works and fixing GRC panel at CLP Substation

·       ABWF and E&M works at PST

·       ABWF, E&M work and RC structure at IW

·       ELS work at AGS

·       ELS work at TTS

·       RC Structure at TTS

·       RC Structure at STB

·       ELS work at Sludge Digester no. 1-3

·       RC Structure at Sludge Digester no. 1-3

·       E&M work at Biogas Holder no. 1

·       ELS works and pipeworks at emergency bypass chamber

11.2            Key Issues for the Coming Month

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3            Monitoring Schedules for the next three months

The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.