11.1
Construction Programme for the Next Three Months
·
E&M works and fixing GRC
panel at CLP Substation
·
ABWF and E&M works at PST
·
ABWF, E&M work and RC
structure at IW
·
Piling at SDB
·
ELS work at AGS
·
ELS work at TTS
·
RC Structure at TTS
·
RC Structure at STB
·
ABWF, E&M work and RC
structure at STB
·
ELS work at Sludge Digester
no. 1-3
·
RC Structure at Sludge
Digester no. 1-3
·
E&M work at Biogas Holder
no. 1
·
ELS works at the existing
inspection chamber & inlet effluent pipes from NSWSPS
11.2
Key Issues for the Coming Month
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3
Monitoring Schedules for the next three months
The tentative schedule for environmental
monitoring in the next three months is provided in Appendix E.