12.
CONCLUSION AND
RECOMMENDATION
12.1.2
Construction noise monitoring
was carried out in the reporting month. No Action / Limit Level exceedance at
CM1, CM2 and CM3 was recorded during the period.
12.1.3
No Action and Limit Level
exceedance was recorded for water quality at M1, M2 and M3 in the reporting
month.
12.1.4
Ardeid night roost monitoring
was carried out in the reporting month. Two active ardeid night roost areas
(ANR1 and ANR2) were observed within the Survey Area. These roosts were located
at the mangrove strips in the east and northeast portions of the Project
boundary. No Action / Limit Level exceedance at NMS1 and NMS2 was recorded
during the period.
12.1.5
Ecological bird monitoring was
carried out in the reporting month. No Action / Limit exceedance for the
ecological monitoring of birds in the reporting month.
12.1.6
Four
environmental site inspections were carried out in the reporting month.
Recommendations on mitigation measures for air quality impact, chemical waste
and construction waste
management and permit/ licenses were given to the Contractor
for remediating the deficiencies identified during the site inspections.
12.1.7
Four
landscape and visual site audits were carried out in the reporting month. No recommendations
on mitigation measures were given to the Contractor for
remediating the deficiencies identified during the site inspections.
12.1.8
No environmental complaint,
notification of summons and successful prosecution was recorded in the
reporting month.
12.2
Comment and Recommendations
12.2.1
The recommended environmental mitigation measures, as proposed in the
EIA report and EM&A Manual shall be effectively implemented to minimize the
potential environmental impacts from the Project. The EM&A programme would
effectively monitor the environmental impacts generated from the construction activities
and ensure the proper implementation of mitigation measures.
12.2.2
According to the environmental site inspections performed in the
reporting month, the following recommendations were provided:
Air
Quality Impact
·
The contractor should increase watering for the
haul road.
Construction
Noise Impact
·
No specific observation was
identified in the reporting month.
Water
Quality Impact
·
No specific observation was
identified in the reporting month.
Chemical
Waste and Construction Waste Management
·
No specific observation was
identified in the reporting month.
Land
Contamination
·
The contractor was reminded to
check the and remove the stagnant water in the drip tray.
Ecological
Impact
·
No specific observation was
identified in the reporting month.
Landscape
and Visual Impact
·
The contractor was reminded to
install additional sticky tape for T232.
Hazard
to Life
·
No specific observation was
identified in the reporting month.
Permit/
Licenses
·
No specific observation was
identified in the reporting month.