11.1
Construction
Programme for the Next Three Months
·
E&M works and fixing GRC panel at
CLP Substation
·
ELS works at the existing inspection
chamber & inlet effluent pipes from NSWSPS
·
ABWF, E&M work and RC structure at
IW
·
ABWF and E&M works at PST
·
Piling and ELS work at SDB
·
Modification of existing Detritor
·
External works at site-wide include
water structure cabinet
·
ELS work and RC structure at AGS
·
ELS work and RC structure at TTS
·
ABWF, E&M work and RC structure at
STB
·
Demolish Existing SDT 1-4 and Gas
Holder GH2
·
ELS work and RC structure at Sludge
Digester no. 1-3
·
E&M work at Biogas Holder no. 1
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.