Table 8 Status of submissions required under the EP
EP Condition (EP-565/2019) |
Submission Title |
Submission
Status |
Condition 2.9 |
Construction Phase
Emergency Response Plan |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.11 |
Pre-construction Ardeid Night Roost Survey Report |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
EM&A Manual Sec. 7.3.3
& 7.3.4 |
Baseline Bird Survey Report |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.12 |
Noise Mitigation Measures Plan |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.13 |
Proposal for Minimization
of Overspill Light to Ecological Sensitive Areas |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Supplementary Contamination Assessment Plan |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment
Report for Main Storeroom & Workshops |
Submitted to EPD
with ET certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for Mechanical
Workshop |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment
Report for Waste Storage Area |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for SAS Thickener
House-1 |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment
Report for SAS Thickener House-2 |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 2.14 |
Contamination Assessment Report for Screening Press House |
Certified by ET Leader and
verified by IEC on 14 Oct 2024 and submitted to EPD on 29 Oct 2024, to be
finalised and made available for public inspection via the dedicated website. |
Condition 2.15 |
Landscape and Visual
Mitigation Plan |
Submitted to EPD
with ET certification and IEC verification, to be finalised and made available
for public inspection via the dedicated website. |
Condition 3.3 |
Baseline Monitoring Report |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 3.4 |
Monthly EM&A Report
(from April 2021 to November 2024) |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
Condition 3.5 |
Quarterly EM&A Report (from April 2021 to September
2024) |
Submitted to EPD with ET
certification and IEC verification, finalised and available for public
inspection via the dedicated website. |
Condition 4.2 |
Environmental Monitoring
Data from April 2021 to November 2024 |
Submitted to EPD
with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |