1
INTRODUCTION
1.1.1
The existing Yuen Long
Sewage Treatment Works (YLSTW) is a secondary sewage treatment works, located
at Yuen Long Industrial Estate serves Yuen Long Town, Yuen Long Industrial
Estate and Kam Tin areas with a design capacity of 70,000 m³ per day. Based on
the latest planning data, the volume of sewage generation from the YLSTW
catchment is estimated to increase to 150,000 m³ per day after 20 years. In addition,
since YLSTW has been operating for over 30 years and most of its facilities are
of out-dated design and reaching the end of their design life, the
environmental facilities of the plant will also be upgraded and hence improving
the adjacent environment through upgrading the YLSTW to Yuen Long Effluent
Polishing Plant (YLEPP). The Location of Proposed Yuen Long Effluent Polishing
Plant is given in Figure 1.
1.1.2
YLSTW will be reconstructed
in two stages to increase its capacity to 150,000 m³ per day. The proposed
works, as Stage 1 of the project, will firstly increase the treatment capacity
to 100,000 m³ per day. In the course of Stage 1 construction, about half of the
existing facilities of YLSTW would be demolished, while the other half would be
kept in operation to maintain the sewage treatment service for Yuen Long area.
This 72-month works contract commenced on 9 November 2020. Demolition of
existing YLSTW for construction of new treatment facilities are in progress.
1.1.3
The Project is a designated
project under Schedule 2 of the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) for which Environmental Impact Assessment (EIA) report and
Environmental Monitoring and Audit (EM&A) Manual was approved by EPD (Register
No.: AEIAR-220/2019) on 25 April 2019. The Environmental Permit (EP) (EP No.
EP-565/2019) was issued by EPD on 26 April 2019. Variation of the Environmental
Permit (EP) (EP No. EP-565/2019/A) was issued by EPD on 26 November 2024.
1.1.4
Fugro Technical Services
Limited was appointed as the Environmental Team (ET) by Drainage Services
Department (DSD) to undertake the Environmental Team services for the Project
and implement the EM&A works under the Contract No. DC/2019/10 Yuen Long
Effluent Polishing Plant -Main Works for Stage 1 (hereinafter referred as “the
Contract”) for the period from July 2020 to 6 July 2023.
1.1.5
Aurecon Hong Kong Limited
(Aurecon) has been appointed as the Environmental Team (ET) by Drainage
Services Department (DSD) to undertake the Environmental Team services for the
Project and implement the EM&A works under the Contract from July 2023. Air
quality, noise, water quality and ecological monitoring, site inspections and
auditing (as scheduled) under EM&A programme with effect from 7 July 2023
was conducted by Aurecon. Aurecon is undertaking the preparation (including
reporting of monitoring results), certification by ET Leader and submission of
this report to EPD.
1.1.6
All ET roles and
responsibilities under the EP for this Project were undertaken by Fugro up to 6
July 2023 and by Aurecon with effect from 7 July 2023. Air quality, noise,
water quality and ecological monitoring, site inspections and auditing (as
scheduled) under EM&A programme up to 6 July 2023 was conducted by Fugro,
and the corresponding monitoring results were shared with Aurecon for the
purposes of reporting in this report.
1.1.7
This
is the 47th Monthly EM&A report to document the findings of site
inspection activities and EM&A programme for this
project from 1 February 2025 to 28 February 2025 (reporting period) and is
submitted to fulfil Condition 3.4 of the EP and Section 12.4.1 of the EM&A
Manual. According to Condition 4 of the EP, electronic reporting is provided on
the internet website to facilitate public inspection of the report.
1.2.1
The Project Organization structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.
1.3
Construction Programme and Activities
1.3.1
The construction programme
of this project is shown in Appendix A.
1.4
Works undertaken during the month
1.4.1
The main construction works
carried out in the reporting period were as follow:
·
Fixing
GRC panel at CLP Substation
·
ELS
works and pipeworks at emergency bypass chamber
·
ABWF,
E&M work and RC structure at IW
·
ABWF
and E&M works at PST
·
ELS
work at SDB
·
External
works at site-wide of predrilling at walkway and water meter cabinet
·
ELS
work at AGS
·
RC
Structure at STB
·
ABWF
and E&M works at STB
·
Demolish
Existing SDT 1-4
·
ELS
work at Sludge Digester no. 1-3
·
E&M
work at Biogas Holder no. 1
1.4.2 The environmental mitigation measures corresponding to the main construction works implemented in the reporting period can be referred to Appendix J.
1.5
Status of Environmental Licences, Notification and
Permits
1.5.1
A summary of the status of the relevant permits, licenses and/or
notifications on environmental protection for this project is presented in Table 2.