11                    FUTURE KEY ISSUES

11.1               Construction Programme for the Next Three Months

·         Fixing GRC panel at CLP Substation

·         ELS works and pipeworks at emergency bypass chamber

·         RC works at emergency bypass chamber

·         ABWF, E&M work and RC structure at IW

·         ABWF and E&M works at PST

·         ELS work at SDB

·         External works at site-wide include water meter cabinet

·         ELS work and RC structure at AGS

·         RC structure at TTS

·         ABWF, E&M work and RC structure at STB

·         Demolish Existing SDT 1-4 and Gas Holder GH2

·         ELS work and RC structure at Sludge Digester no. 1-3

·         E&M work at Biogas Holder no. 1

11.2               Key Issues for the Coming Month

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3               Monitoring Schedules for the next three months

The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.