11.1
Construction
Programme for the Next Three Months
·
Fixing
GRC panel at CLP Substation
·
ELS
works and pipeworks at emergency bypass chamber
·
RC
works at emergency bypass chamber
·
ABWF,
E&M work and RC structure at IW
·
ABWF
and E&M works at PST
·
ELS
work at SDB
·
External
works at site-wide include water meter cabinet
·
ELS
work and RC structure at AGS
·
RC
structure at TTS
·
ABWF,
E&M work and RC structure at STB
·
Demolish
Existing SDT 1-4 and Gas Holder GH2
·
ELS
work and RC structure at Sludge Digester no. 1-3
·
E&M
work at Biogas Holder no. 1
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.