11.1
Construction
Programme for the Next Three Months
·
Fixing GRC panel at CLP
Substation
·
Pipeworks and manhole installation at
emergency bypass chamber
·
ABWF and E&M works at IW
·
ABWF and E&M works at PST
·
ELS work at SDB
·
External works at site-wide
include water meter cabinet
·
ELS work and RC structure at
AGS
·
RC structure at TTS
·
ABWF, E&M work and RC
structure at STB
·
Demolish Existing SDT 1-4 and
Gas Holder GH2
·
RC structure at Sludge
Digester no. 1-3 with PP1
·
RC work at Biogas Holder no.
2-3 foundation
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.