Table 2 Main Construction Works carried out in the Reporting Period
January 2025 |
February 2025 |
March 2025 |
·
Fixing GRC panel at CLP Substation ·
ELS works and pipeworks
at emergency bypass chamber ·
ABWF, E&M work and RC structure at IW ·
ABWF and E&M works at PST ·
ELS work at SDB ·
External works at site-wide of predrilling at
walkway and water meter cabinet ·
ELS work at AGS ·
ELS work at TTS ·
RC Structure at STB ·
Demolish Existing SDT 1-4 ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Disposal of construction waste as indicated in Appendix F.
|
·
Fixing GRC panel at CLP Substation ·
ELS works and pipeworks
at emergency bypass chamber ·
ABWF, E&M work and RC structure at IW ·
ABWF and E&M works at PST ·
ELS work at SDB ·
External works at site-wide of predrilling at
walkway and water meter cabinet ·
ELS work at AGS ·
RC Structure at STB ·
ABWF and E&M works at STB ·
Demolish Existing SDT 1-4 ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Disposal of construction waste as indicated in Appendix F.
|
·
Fixing GRC panel at CLP Substation ·
ELS works and pipeworks
at emergency bypass chamber ·
ABWF, E&M work and RC structure at IW ·
ABWF and E&M works at PST ·
ELS work at SDB ·
External works at site-wide of predrilling at
walkway and water meter cabinet ·
ELS work at AGS ·
RC structure at TTS ·
RC, ABWF and E&M works at STB ·
Demolish Existing SDT 1-4 ·
ELS work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Disposal of construction waste as indicated in Appendix F. |