11.1
Construction
Programme for the Next Three Months
·
Fixing GRC panel at CLP
Substation
·
Fixing GRC panel at CLP
Substation
·
Pipe works and manhole
installation at emergency bypass chamber
·
ABWF, E&M and sheet pile
works at IW
·
ABWF, E&M and sheet pile
works at PST
·
ELS work and RC
work at SDB
·
Predrill works at ADB
·
External works at site-wide
include water meter cabinet
·
ELS work and RC structure at
AGS
·
RC structure at TTS
·
ABWF and E&M
work at STB
·
Demolish Gas Holder GH2
·
ELS work at UC3
·
RC structure at Sludge
Digester no. 1-3 with PP1
·
ELS work at Sludge
Digester no. 4-6
·
RC work at Biogas Holder no.
2-3 foundation
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.