11                    FUTURE KEY ISSUES

11.1               Construction Programme for the Next Three Months

·      Fixing GRC panel at CLP Substation

·      Fixing GRC panel at CLP Substation

·      Pipe works and manhole installation at emergency bypass chamber

·      ABWF, E&M and sheet pile works at IW

·      ABWF, E&M and sheet pile works at PST

·      ELS work and RC work at SDB

·      Predrill works at ADB

·      External works at site-wide include water meter cabinet

·      ELS work and RC structure at AGS

·      RC structure at TTS

·      ABWF and E&M work at STB

·      Demolish Gas Holder GH2

·      ELS work at UC3

·      RC structure at Sludge Digester no. 1-3 with PP1

·      ELS work at Sludge Digester no. 4-6

·      RC work at Biogas Holder no. 2-3 foundation

11.2               Key Issues for the Coming Month

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3               Monitoring Schedules for the next three months

The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.