8.1.2
No
Action and Limit Level exceedance was recorded for water quality in the
reporting period.
8.1.3
No
Action / Limit exceedance was recorded for noise levels at stations (NMS1 and
NMS2) in close proximity to the active ardeid night roosts in the monitoring
period.
6.1.1
No
Action / Limit exceedance for the ecological monitoring of birds in the reporting period.
8.1.4
13
environmental site inspections and 13 landscape and visual site audits were
carried out in the reporting period. Recommendations on mitigation measures
were given to the Contractor for remediating the deficiencies identified during
the site inspections.
8.1.5
No
environmental complaints, notification of summons and successful prosecutions
were recorded in the reporting period.
8.1.6
The
EM&A methodology has been effective in monitoring the environmental impacts
of the Project and the effectiveness of the mitigation measures. The data
collected were useful in determining whether the Project had caused
unacceptable impacts on the sensitive receivers. Analysis of all EM&A data
collected throughout the baseline and the impact monitoring periods
demonstrated the environmental acceptability of the Project.
8.2.1 According to the environmental site inspections performed in the reporting period, the following recommendations were provided:
Air Quality
Impact
·
Insufficient watering for the haul road.Sufficient
watering should be applied for the works of sheet piling.
·
Open stockpiles at SDT should be avoided or covered
Construction
Noise Impact
·
The Contractor was reminded to enclose the silentup at northwest of the Site.
·
The silentup at northwest of the
Site should be enclosed.
Water
Quality Impact
·
No specific observation was
identified in the reporting period.
Chemical
Waste and Construction Waste Management
·
The Contractor was reminded to remove the construction waste
from the Site timely
Land
Contamination
·
The drip trays should be checked and cleaned regularly
Ecological
Impact
·
No specific observation was
identified in the reporting period.
Landscape
and Visual Impact
·
No specific observation was
identified in the reporting period.
Hazard to
Life
·
No specific observation was
identified in the reporting period.
Permit/
Licenses
·
The size of NRMM label for the sheet piling machine at SDB is
incorrect.
·
NRMM label should be provided for the excavator at AGS.
Other
·
The Contractor was reminded to remove the stagnant water at
the Main Entrance of the Site.