8.1.1
Site
audits were carried out by ET on weekly basis at least once per week to monitor
the implementation of proper environmental management practices and mitigation
measures in the Project site.
8.1.2
In
the reporting month, five site inspections were carried out on 2, 9, 17, 23 and
30 July 2025.
8.1.3
No outstanding issues were reported during the reporting month. The ET
Leader’s Site Environmental Audit are summarized in Appendix M.
8.2
Advice on the Solid and Liquid Waste Management
Status
8.2.1
The Contractor registered
as a chemical waste producer for the Contract. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
8.2.2
The management of waste
generated by the construction is presented in Table
27.
8.2.3
The monthly summary of
waste flow table is detailed in Appendix
I.
8.2.4
If off-site disposal is
required, the excavated marine mud from the land-based works shall be disposed
of at the designated disposal sites within Hong Kong as allocated by the Marine
Fill Committee or other locations as agreed by the Director. The Contractor
shall ensure no spilling and overflowing of materials during loading /
unloading / transportation is allowed.
8.2.5
The Contractor was reminded
that chemical waste should be properly handled temporarily in designated
chemical waste storage area on site in accordance with the Code of Practice on
the Packing, Labelling and Storage of Chemical Waste.
9.