This Monthly Environmental
Monitoring and Audit (EM&A) Report is prepared for Contract No. SPW 02/2023
“Environmental Team for Construction of Yuen Long Effluent Polishing Plant
Stage 1”. Drainage Services Department (DSD) has appointed Aurecon Hong Kong
Limited (Aurecon) to undertake the Environmental Team services for the project
and implement the EM&A works.
This is the 52nd
Monthly EM&A Report for the construction phase which summaries findings of
the EM&A programme during the reporting period from 1 July 2025 to 31 July
2025. As informed by the Contractor, major activities in the reporting month
were:
· Fixing GRC panel at CLP
Substation
· Pipe works and manhole
installation at emergency bypass chamber
· ABWF, E&M and sheet
pile works at IW
· ABWF, E&M and sheet
pile works at PST
· ELS work at SDB
· External works at site-wide
of predrilling at walkway and water meter cabinet
· ELS work at AGS
· RC structure at TTS
· ABWF and E&M works at
STB
· Demolish Existing SDT 1-4
· RC work at Sludge
Digester no. 1-3
· E&M work at Biogas
Holder no. 1
· Disposal of construction
waste as indicated in Appendix I.
Breaches of Environmental Quality Performance
Limits (AL levels)
No Action and Limit Level exceedance was
recorded for air quality monitoring and construction noise monitoring in the
reporting month.
No Action and Limit Level exceedance was
recorded for water quality monitoring in the reporting month.
No Action / Limit exceedance was recorded for
noise levels at stations (NMS1 and NMS2) in close proximity to the two active
ardeid night roosts (ANR1 and ANR2) observed within the Survey Area during the
reporting month.
No Action / Limit exceedance for the
ecological monitoring of birds in the reporting month.
No corrective actions were required according
to the Event and Action Plans for the Monitoring Parameters.
Land Contamination
Regular site inspection was
carried out to ensure the recommended mitigation measures are properly
implemented. The signed final Contamination Assessment Report (CAR) for “Main
Storeroom & Workshops”, “Mechanical Workshop”, “Waste Storage Area”, “SAS
Thickener House-1”, “SAS Thickener House-2”and “Screening Press House” were
submitted to EPD respectively on 1st November 2021, 23rd
November 2021, 29th April 2022, 6th July 2022, 19th
June 2023 and 29th October 2024. No contaminated soil and ground
water was found within the Main Storeroom & Workshop, Mechanical Workshop,
Waste Storage Area, SAS Thickener House-1, SAS Thickener House-2 and Screening
Press House, and no remedial action is required for these locations.
Complaint Log
No complaints were received
in the reporting period.
Notifications of Summons and Successful
Prosecutions
No notifications of summons
and successful prosecutions were received in the reporting period.
Reporting Change
There were no reporting
changes during the reporting month.
Future Key Issues
The main works will be
anticipated in the next three months are as follow:
· Fixing GRC panel at CLP
Substation
· Pipe works and manhole
installation at emergency bypass chamber
· ABWF, E&M and sheet
pile works at IW
· ABWF, E&M and sheet
pile works at PST
· ELS work and RC
work at SDB
· Predrill works at ADB
· External works at site-wide
include water meter cabinet
· ELS work and RC structure
at AGS
· RC structure at TTS
· ABWF and E&M
work at STB
· Demolish Gas Holder GH2
· ELS work at UC3
· RC structure at Sludge
Digester no. 1-3 with PP1
· ELS work at Sludge
Digester no. 4-6
· RC work at Biogas Holder
no. 2-3 foundation