12.
CONCLUSION AND
RECOMMENDATION
12.1.2
Construction noise monitoring
was carried out in the reporting month. No Action / Limit Level exceedance at
CM1, CM2 and CM3 was recorded during the period.
12.1.3
No Action and Limit Level
exceedance was recorded for water quality at M1, M2 and M3 in the reporting
month.
12.1.4
Ardeid night roost monitoring
was carried out in the reporting month. Two active ardeid night roost areas
(ANR1 and ANR2) were observed within the Survey Area. These roosts were located
at the mangrove strips in the east and northeast portions of the Project
boundary. No Action / Limit Level exceedance at NMS1 and NMS2 was recorded
during the period.
12.1.5
Ecological bird monitoring was
carried out in the reporting month. No Action / Limit exceedance for the
ecological monitoring of birds in the reporting month.
12.1.6
Four environmental
site inspections were carried out in the reporting month. Recommendations on
mitigation measures for air
quality impact, chemical waste and construction waste management and permit/ licenses were given to the Contractor for remediating the deficiencies
identified during the site inspections.
12.1.7
Four landscape and
visual site audits were carried out in the reporting month. No recommendations
on mitigation measures were given to the Contractor for remediating the deficiencies identified
during the site inspections.
12.1.8
No environmental complaint,
notification of summons and successful prosecution was recorded in the
reporting month.
12.2
Comment and
Recommendations
12.2.1
The recommended environmental mitigation measures, as
proposed in the EIA report and EM&A Manual shall be effectively implemented
to minimize the potential environmental impacts from the Project. The EM&A
programme would effectively monitor the environmental impacts generated from
the construction activities and ensure the proper implementation of mitigation
measures.
12.2.2
According to the environmental site inspections
performed in the reporting month, the following recommendations were provided:
Air Quality
Impact
· Sufficient
watering should be provided for the haul road.
Construction
Noise Impact
· No
specific observation was identified in the reporting month.
Water Quality
Impact
· No
specific observation was identified in the reporting month.
Chemical Waste
and Construction Waste Management
· No
specific observation was identified in the reporting month.
Land
Contamination
· No
specific observation was identified in the reporting month.
Ecological
Impact
· No
specific observation was identified in the reporting month.
Landscape and
Visual Impact
· No
specific observation was identified in the reporting month.
Hazard to Life
· No
specific observation was identified in the reporting month.
Permit/ Licenses
· No
specific observation was identified in the reporting month.
Other
· No
specific observation was identified in the reporting month.