8.1.2
No Action
and Limit Level exceedance was recorded for water quality in the reporting
period.
8.1.3
No
Action / Limit exceedance was recorded for noise levels at stations (NMS1 and
NMS2) in close proximity to the active ardeid night roosts in the monitoring
period.
6.1.1
No
Action / Limit exceedance for the ecological monitoring of birds in the reporting period.
8.1.4
14
environmental site inspections and 14 landscape and visual site audits were
carried out in the reporting period. Recommendations on mitigation measures
were given to the Contractor for remediating the deficiencies identified during
the site inspections.
8.1.5
No
environmental complaints, notification of summons and successful prosecutions
were recorded in the reporting period.
8.1.6
The
EM&A methodology has been effective in monitoring the environmental impacts
of the Project and the effectiveness of the mitigation measures. The data
collected were useful in determining whether the Project had caused
unacceptable impacts on the sensitive receivers. Analysis of all EM&A data
collected throughout the baseline and the impact monitoring periods
demonstrated the environmental acceptability of the Project.
8.2.1 According to the environmental site inspections performed in the reporting period, the following recommendations were provided:
Air Quality
Impact
·
Sufficient
watering should be provided for the haul road.
Construction
Noise Impact
·
The
silentup at northwest of the Site should be enclosed.
Water
Quality Impact
·
No specific observation was
identified in the reporting period.
Chemical
Waste and Construction Waste Management
·
Construction
waste and domestic waste should be stored separately.
Land Contamination
·
No specific observation was
identified in the reporting period.
Ecological
Impact
·
No specific observation was
identified in the reporting period.
Landscape
and Visual Impact
·
Two dead branches of T133 are recommended
for removal.
·
The Contractor was reminded to prune the
broken part of Tree T142.
·
The broken branch should be pruned back to
the union. Pruning shall follow “Guild lines on Tree Pruning” of GLTMS, DevB (Dec 2023)
“Guild lines on Tree Preservation during
Development” GLTMS DevB shall be followed to avoid
mechanical injury to trees during construction activities.
Hazard to
Life
·
No specific observation was
identified in the reporting period.
Permit/
Licenses
·
The color of NRMM label for the generator at SDB should be green.
·
A
new NRMM label should be provided for the generator at EBC.
Other
·
No specific observation was
identified in the reporting period.