Table 6 Observations and Recommendations of Site Audit
|
Date |
Observations and Recommendations |
Follow-up |
|
|
Air
Quality |
20 August 2025 |
Observation
1: Sufficient
watering should be provided for the haul road. |
Watering
was increased. |
|
Noise |
9 September 2025 |
Observation 1: The silentup at northwest of the Site should be enclosed. |
The silentup was enclosed. |
|
Water
Quality |
N/A |
||
|
Chemical and Construction Waste
Management |
9 September 2025 |
Reminder 1: Construction
waste and domestic waste should be stored separately |
Covered rubbish bin for domestic waste was
provided |
|
Land
Contamination |
N/A |
||
|
Ecological Impact |
N/A |
||
|
Landscape
and Visual Impact |
9
September 2025 |
Reminder
1: Two dead branches of T133 are recommended for
removal. |
Two
dead branches of T133 were removed. |
|
17 September 2025 |
Reminder 1: The Contractor was remined to prune the broken part of Tree T142. |
Broken part of Tree T142 was removed. |
|
|
23
September 2025 |
Reminder
1: The broken branch should be pruned back to the
union. Pruning shall follow “Guild lines on Tree Pruning” of GLTMS, DevB (Dec 2023) “Guild lines on Tree
Preservation during Development” GLTMS DevB shall
be followed to avoid mechanical injury to tress during construction activities. |
Broken
part of the tree was removed. |
|
|
Permit / Licenses |
30 July
2025 |
Observation 1: The color of
NRMM label for the generator at SDB is correct. |
A new NRMM label was provided |
|
3
September 2025 |
Reminder 1: NRMM
label should be provided for the generator at EBC. |
New
NRMM label was provided. |
|
|
Other |
N/A |
||