1
INTRODUCTION
1.1.1
The existing Yuen Long Sewage Treatment Works (YLSTW) is a secondary
sewage treatment works, located at Yuen Long Industrial Estate serves Yuen Long
Town, Yuen Long Industrial Estate and Kam Tin areas with a design capacity of
70,000 m³ per day. Based on the latest planning data, the volume of sewage
generation from the YLSTW catchment is estimated to increase to 150,000 m³ per
day after 20 years. In addition, since YLSTW has been operating for over 30
years and most of its facilities are of out-dated design and reaching the end
of their design life, the environmental facilities of the plant will also be upgraded
and hence improving the adjacent environment through upgrading the YLSTW to
Yuen Long Effluent Polishing Plant (YLEPP). The Location of Proposed Yuen Long
Effluent Polishing Plant is given in Figure
1.
1.1.2
YLSTW will be reconstructed in two stages to increase its capacity to
150,000 m³ per day. The proposed works, as Stage 1 of the project, will firstly
increase the treatment capacity to 100,000 m³ per day. In the course of Stage 1
construction, about half of the existing facilities of YLSTW would be
demolished, while the other half would be kept in operation to maintain the
sewage treatment service for Yuen Long area. This 72-month works contract
commenced on 9 November 2020. Demolition of existing YLSTW for construction of
new treatment facilities are in progress.
1.1.3
The Project is a designated project under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) for which
Environmental Impact Assessment (EIA) report and Environmental Monitoring and Audit
(EM&A) Manual was approved by EPD (Register No.: AEIAR-220/2019) on 25
April 2019. The Environmental Permit (EP) (EP No. EP-565/2019) was issued by
EPD on 26 April 2019. Variation of the Environmental Permit (EP) (EP No.
EP-565/2019/A) was issued by EPD on 26 November 2024.
1.1.4
Fugro Technical Services Limited was appointed as the Environmental Team
(ET) by Drainage Services Department (DSD) to undertake the Environmental Team
services for the Project and implement the EM&A works under the Contract
No. DC/2019/10 Yuen Long Effluent Polishing Plant -Main Works for Stage 1
(hereinafter referred as “the Contract”) for the period from July 2020 to 6
July 2023.
1.1.5
Aurecon Hong Kong Limited (Aurecon) has been appointed as the
Environmental Team (ET) by Drainage Services Department (DSD) to undertake the
Environmental Team services for the Project and implement the EM&A works
under the Contract from July 2023. Air quality, noise, water quality and
ecological monitoring, site inspections and auditing (as scheduled) under
EM&A programme with effect from 7 July 2023 was conducted by Aurecon.
Aurecon is undertaking the preparation (including reporting of monitoring
results), certification by ET Leader and submission of this report to EPD.
1.1.6
All
ET roles and responsibilities under the EP for this Project were undertaken by
Fugro up to 6 July 2023 and by Aurecon with effect from 7 July 2023. Air
quality, noise, water quality and ecological monitoring, site inspections and
auditing (as scheduled) under EM&A programme
up to 6 July 2023 was conducted by Fugro, and the corresponding monitoring
results were shared with Aurecon for the purposes of reporting in this report.
1.1.7
This
is the 56th Monthly EM&A report to document the findings of site
inspection activities and EM&A programme for this
project from 1 November 2025 to
30 November
2025 (reporting period) and is submitted to fulfil Condition 3.4 of the EP and
Section 12.4.1 of the EM&A Manual. According to Condition 4 of the EP,
electronic reporting is provided on the internet website to facilitate public
inspection of the report.
1.2
Project
Organization
1.2.1
The Project Organization structure is shown in Appendix B. The key personnel contact
names and numbers are summarized in Table 1.
1.3
Construction
Programme and Activities
1.3.1
The construction programme of this project is shown in Appendix A.
1.4
Works
undertaken during the month
1.4.1
The
main construction works carried out in the reporting period were as follow:
·
Fixing
GRC panel at CLP Substation
·
ELS
Works for Modification of Existing Inspection Chamber and Inlet Effluent Pipes
from NSWSPS
·
T&C
Works at IW
·
ELS
works at IW (Remaining area)
·
ELS
works at PST Stage 2
·
ELS
work at SDB
·
demolition
work of existing building at ADB
·
External
works at site-wide include water meter cabinet
·
RC
works at AGS
·
RC
structure at TTS
·
ABWF
and E&M works at STB
·
Demolish
Existing SDT 1-4
·
RC work
at Sludge Digester no. 1-3
·
T&C
work at Biogas Holder no. 1
1.4.2
The
environmental mitigation measures corresponding to the main construction works
implemented in the reporting period can be referred to Appendix J.
1.5
Status of
Environmental Licences, Notification and Permits
1.5.1
A summary of the status of the relevant permits, licenses and/or notifications
on environmental protection for this project is presented in Table 2.