11                    FUTURE KEY ISSUES

11.1               Construction Programme for the Next Three Months

The main works anticipated in the next three months are as follow:

·      Fixing GRC panel at CLP Substation

·      ELS Works and Pipe works for Modification of Existing Inspection Chamber and Inlet Effluent Pipes from NSWSPS

·      T&C Works at IW

·      RC, ABWF and E&M works at IW (Remaining area)

·      RC, ABWF and E&M works at PST Stage 2

·      ELS work and RC work at SDB

·      Predrill works and ELS work at ADB

·      External works at site-wide include water meter cabinet

·      RC structure at AGS

·      RC structure at TTS

·      ABWF and E&M work at STB

·      RC and E&M work at H2S

·      ELS work at UC3

·      RC structure at Sludge Digester no. 1-3 with PP1

·      ELS work at Sludge Digester no. 4-6

·      RC work at Biogas Holder no. 2-3 foundation

11.2               Key Issues for the Coming Month

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3               Monitoring Schedules for the next three months

The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.