11.1
Construction
Programme for the Next Three Months
The main
works anticipated in the next three months are as follow:
· Fixing GRC panel at CLP Substation
· ELS Works and Pipe works for Modification of Existing
Inspection Chamber and Inlet Effluent Pipes from NSWSPS
· T&C Works at IW
· RC, ABWF and E&M works at IW (Remaining area)
· RC, ABWF and E&M works at PST Stage 2
· ELS work and RC work at SDB
· Predrill works and ELS work at ADB
· External works at site-wide include water meter
cabinet
· RC structure at AGS
· RC structure at TTS
· ABWF and E&M work at STB
· RC and E&M work at H2S
· ELS work at UC3
· RC structure at Sludge Digester no. 1-3 with PP1
· ELS work at Sludge Digester no. 4-6
· RC work at Biogas Holder no. 2-3 foundation
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.