This Monthly Environmental
Monitoring and Audit (EM&A) Report is prepared for Contract No. SPW 01/2025
“Environmental Team for Construction of Yuen Long Effluent Polishing Plant
Stage 1”. Drainage Services Department (DSD) has appointed Aurecon Hong Kong
Limited (Aurecon) to undertake the Environmental Team services for the project
and implement the EM&A works.
This is the 56th Monthly EM&A Report
for the construction phase which summaries findings of the EM&A programme
during the reporting period from 1 November 2025 to 30 November 2025. As informed by the
Contractor, major activities in the reporting month were:
· Fixing GRC panel at CLP
Substation
· ELS Works for Modification
of Existing Inspection Chamber and Inlet Effluent Pipes from NSWSPS
· T&C Works at IW
· ELS works at IW (Remaining
area)
· ELS works at PST Stage 2
· ELS work at SDB
· demolition work of existing
building at ADB
· External works at site-wide
include water meter cabinet
· RC works at AGS
· RC structure at TTS
· ABWF and E&M works at STB
· Demolish Existing SDT 1-4
· RC work at Sludge
Digester no. 1-3
· T&C work at Biogas
Holder no. 1
· Disposal of construction
waste as indicated in Appendix I.
Breaches of Environmental Quality Performance
Limits (AL levels)
No Action and Limit Level exceedance was
recorded for air quality monitoring and construction noise monitoring in the
reporting month.
No Action and Limit Level exceedance was
recorded for water quality monitoring in the reporting month.
No Action / Limit exceedance was recorded for
noise levels at stations (NMS1 and NMS2) in close proximity to the two active
ardeid night roosts (ANR1 and ANR2) observed within the Survey Area during the
reporting month.
No Action / Limit exceedance for the
ecological monitoring of birds in the reporting month.
No corrective actions were required according
to the Event and Action Plans for the Monitoring Parameters.
Land Contamination
Regular site inspection was
carried out to ensure the recommended mitigation measures are properly implemented.
The signed final Contamination Assessment Report (CAR) for “Main Storeroom
& Workshops”, “Mechanical Workshop”, “Waste Storage Area”, “SAS Thickener
House-1”, “SAS Thickener House-2”and “Screening Press House” were submitted to
EPD respectively on 1st November 2021, 23rd November
2021, 29th April 2022, 6th July 2022, 19th
June 2023 and 29th October 2024. No contaminated soil and ground
water was found within the Main Storeroom & Workshop, Mechanical Workshop,
Waste Storage Area, SAS Thickener House-1, SAS Thickener House-2 and Screening
Press House, and no remedial action is required for these locations.
Complaint Log
No complaints were received
in the reporting period.
Notifications of Summons and Successful
Prosecutions
No notifications of summons
and successful prosecutions were received in the reporting period.
Reporting Change
There were no reporting
changes during the reporting month.
Future Key Issues
The main works anticipated
in the next three months are as follow:
·
Fixing GRC panel at CLP Substation
·
ELS Works and Pipe works for Modification of Existing Inspection Chamber
and Inlet Effluent Pipes from NSWSPS
·
T&C Works at IW
·
RC, ABWF and E&M works at IW (Remaining area)
·
RC, ABWF and E&M works at PST Stage 2
·
ELS work and RC work at SDB
·
Predrill works and ELS work at ADB
·
External works at site-wide include water meter cabinet
·
RC structure at AGS
·
RC structure at TTS
·
ABWF and E&M work at STB
·
RC and E&M work at H2S
·
ELS work at UC3
·
RC structure at Sludge Digester no. 1-3 with PP1
·
ELS work at Sludge Digester no. 4-6
·
RC work at Biogas Holder no. 2-3 foundation