10
IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURE
10.1
Implementation Status of Environmental Protection
and Pollution Control / Mitigation Measures
The Contractor had implemented environmental protection and pollution
control / mitigation measures as stated in the EIA Report, the EP and EM&A
Manual. Appendix J summarized
the Implementation Status of Environmental Mitigation Measures.
Further to the variation of the Environmental Permit
(EP) (EP No. EP-565/2019/A) issued by EPD on 26 November 2024, the tides predicted
by the Hong Kong Observatory for the tidal station at Tsim Bei Tsui for the
upcoming month is presented in Appendix Q.
The status of required
submissions under the EP as of the reporting period are summarized in Table 28.