11.1
Construction
Programme for the Next Three Months
The main
works anticipated in the next three months are as follow:
Contract DC/2019/10:
·
Fixing
GRC panel at CLP Substation
·
ELS
Works and Pipe works for Modification of Existing Inspection Chamber and Inlet
Effluent Pipes from NSWSPS
·
T&C
Works at IW
·
RC,
ABWF and E&M works at IW (Remaining area)
·
RC,
ABWF and E&M works at PST Stage 2
·
ELS
work and RC work at SDB
·
Predrill
works and ELS work at ADB
·
External
works at site-wide include water meter cabinet
·
RC
structure at AGS
· RC structure at TTS
· ABWF and E&M work at STB
·
RC
and E&M work at H2S
·
ELS
work at UC3
·
RC
structure at Sludge Digester no. 1-3 with PP1
·
ELS
work at Sludge Digester no. 4-6
· RC work at Biogas Holder no. 2-3 foundation
Contract DE/2020/01:
· Installation of PV panels at IW
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction activities
are mainly associated with construction dust, construction noise, waste
management, ecology, land contamination and landscape and visual impact issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.