Table 2 Main Construction Works carried out in the Reporting Period
|
October 2025 |
November 2025 |
December 2025 |
|
Contract
DC/2019/10: ·
Fixing GRC panel at CLP Substation ·
Pipe works and manhole installation at emergency bypass chamber ·
ABWF, E&M and sheet pile works at IW ·
ABWF, E&M and sheet pile works at PST ·
ELS work at SDB ·
External works at site-wide of predrilling at walkway and water
meter cabinet ·
ELS work at AGS ·
RC structure at TTS ·
ABWF and E&M works at STB ·
Demolish Existing SDT 1-4 ·
RC work at Sludge Digester no. 1-3 ·
E&M work at Biogas Holder no. 1 ·
Zone SD Waterproofing and Backfill for Remove S2 ·
Disposal of construction waste as indicated in Appendix F. |
Contract
DC/2019/10: ·
Fixing GRC panel at CLP Substation ·
ELS Works for Modification of Existing Inspection Chamber and Inlet
Effluent Pipes from NSWSPS ·
T&C Works at IW ·
ELS works at IW (Remaining area) ·
ELS works at PST Stage 2 ·
ELS work at SDB ·
Demolition work of existing building at ADB ·
External works at site-wide include water meter cabinet ·
RC works at AGS ·
RC structure at TTS ·
ABWF and E&M works at STB ·
Demolish Existing SDT 1-4 ·
RC work at Sludge Digester no. 1-3 ·
T&C work at Biogas Holder no.1 ·
Disposal of construction waste as indicated in Appendix F.
|
Contract
DC/2019/10: ·
Fixing GRC panel at CLP Substation ·
ELS Works and Pipe works for Modification of Existing Inspection
Chamber and Inlet Effluent Pipes from NSWSPS ·
T&C Works at IW ·
RC, ABWF and E&M works at IW (Remaining area) ·
RC, ABWF and E&M works at PST Stage 2 ·
ELS work and RC work at SDB ·
Predrill works and ELS work at ADB ·
External works at site-wide include water meter cabinet ·
RC structure at AGS ·
RC structure at TTS ·
ABWF and E&M work at STB ·
RC and E&M work at H2S ·
ELS work at UC3 ·
RC structure at Sludge Digester no. 1-3 with PP1 ·
ELS work at Sludge Digester no. 4-6 ·
RC work at Biogas Holder no. 2-3 foundation ·
Disposal of construction waste as indicated in Appendix
F. Contract
DE/2020/01: ·
Installation of PV panels ·
Disposal of construction waste as indicated in Appendix
F. |