1
INTRODUCTION
1.1.1
The existing Yuen Long Sewage Treatment Works (YLSTW) is a secondary
sewage treatment works, located at Yuen Long Industrial Estate serves Yuen Long
Town, Yuen Long Industrial Estate and Kam Tin areas with a design capacity of
70,000 m³ per day. Based on the latest planning data, the volume of sewage
generation from the YLSTW catchment is estimated to increase to 150,000 m³ per
day after 20 years. In addition, since YLSTW has been operating for over 30
years and most of its facilities are of out-dated design and reaching the end
of their design life, the environmental facilities of the plant will also be
upgraded and hence improving the adjacent environment through upgrading the
YLSTW to Yuen Long Effluent Polishing Plant (YLEPP). The Location of Proposed
Yuen Long Effluent Polishing Plant is given in Figure 1.
1.1.2
YLSTW will be reconstructed in two stages to increase its capacity to
150,000 m³ per day. The proposed works, as Stage 1 of the project, will firstly
increase the treatment capacity to 100,000 m³ per day. In the course of Stage 1
construction, about half of the existing facilities of YLSTW would be
demolished, while the other half would be kept in operation to maintain the
sewage treatment service for Yuen Long area. This 72-month works contract
(Contract DC/2019/10) commenced on 9 November 2020. Demolition of existing
YLSTW for construction of new treatment facilities are in progress
1.1.3
Under Contract DE/2020/01, this 54-month works
contract commenced on 13 June 2022. Design and installation of E&M system,
and the supply and installation of PV panels are in progress.
1.1.4
The Project is a designated project under Schedule 2 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) for which
Environmental Impact Assessment (EIA) report and Environmental Monitoring and
Audit (EM&A) Manual was approved by EPD (Register No.: AEIAR-220/2019) on
25 April 2019. The Environmental Permit (EP) (EP No. EP-565/2019) was issued by
EPD on 26 April 2019. Variation of the Environmental Permit (EP) (EP No.
EP-565/2019/A) was issued by EPD on 26 November 2024.
1.1.5
Fugro Technical Services Limited was appointed as the Environmental Team
(ET) by Drainage Services Department (DSD) to undertake the Environmental Team
services for the Project and implement the EM&A works under the Contract
No. DC/2019/10 Yuen Long Effluent Polishing Plant -Main Works for Stage 1
(hereinafter referred as “the Contract”) for the period from July 2020 to 6
July 2023.
1.1.6
Aurecon Hong Kong Limited (Aurecon) has been appointed as the
Environmental Team (ET) by Drainage Services Department (DSD) to undertake the
Environmental Team services for the Project and implement the EM&A works
under the Contract from July 2023. Air quality, noise, water quality and
ecological monitoring, site inspections and auditing (as scheduled) under
EM&A programme with effect from 7 July 2023 was conducted by Aurecon. Aurecon is undertaking the preparation (including
reporting of monitoring results), certification by ET Leader and submission of
this report to EPD.
1.1.7
All ET roles and responsibilities under the EP for
this Project were undertaken by Fugro up to 6 July 2023 and by Aurecon with
effect from 7 July 2023. Air quality, noise, water
quality and ecological monitoring, site inspections and auditing (as scheduled)
under EM&A programme up to 6 July 2023 was conducted by Fugro, and the
corresponding monitoring results were shared with Aurecon for the purposes of
reporting in this report.
1.1.8
This
is the 59th Monthly EM&A report to document the findings of site
inspection activities and EM&A programme for this project from 1 February 2026 to
28 February
2026 (reporting period) and is submitted to fulfil Condition 3.4 of the EP and
Section 12.4.1 of the EM&A Manual. According to Condition 4 of the EP,
electronic reporting is provided on the internet website to facilitate public
inspection of the report.
1.2
Project
Organization
1.2.1
The Project Organization structure is shown in Appendix B. The key personnel contact
names and numbers are summarized in Table 1.
1.3
Construction
Programme and Activities
1.3.1
The construction programme of this project is shown in Appendix A.
1.4
Works undertaken
during the month
1.4.1
The
main construction works carried out in the reporting period were as follow:
Contract DC/2019/10:
·
Fixing
GRC panel at CLP Substation
·
ELS
Works and Pipe works for Modification of Existing Inspection Chamber and Inlet
Effluent Pipes from NSWSPS
·
ABWF
and T&C Works at IW
·
ELS
works at PST Stage 2
·
RC
works at PST Stage 2
·
RC
works at SDB
·
ELS
works at ADB and Underpass
·
RC
works at AGS
·
RC
structure at TTS
·
ABWF
and E&M works at STB
·
ELS
work at Sludge Digester no. 4 -6 and UC4
·
E&M
wok at Sludge Digester no. 1-3
·
T&C
work at Biogas Holder no.1
Contract DE/2020/01:
·
Installation
of PV panels at IW
1.4.2
The
environmental mitigation measures corresponding to the main construction works
implemented in the reporting period can be referred to Appendix J.
1.5
Status of
Environmental Licences, Notification and Permits
1.5.1
A summary of the status of the relevant permits, licenses and/or
notifications on environmental protection for this project is presented in Table 2.