11.1
Construction
Programme for the Next Three Months
The main
works anticipated in the next three months are as follow:
Contract DC/2019/10:
· Fixing GRC panel at CLP Substation
· Pipe works for Modification of Existing Inspection
Chamber and Inlet Effluent Pipes from NSWSPS
· T&C Works at IW
· Temporary Road Works at IW (South Side) for FS Inspection
· ABWF and E&M works at IW (Remaining area)
· ELS and RC works at PST Stage 2
· RC work at SDB
· Driven H-Pile works at ADB
· External UU works at site-wide
· RC structure at AGS
· RC structure at TTS and Water Tightness Test
· ABWF, E&M and T&C work at STB
· ELS work at UC2 and UC3
· E&M, Water Tightness Test and Lining work at
Sludge Digester no. 1-3
· RC work at PP1
· ELS work at Sludge Digester no. 4-6 and UC4
· E&M work at Biogas Holder no.2
Contract DE/2020/01:
· Installation of PV panels at IW
11.2
Key Issues
for the Coming Month
Potential environmental impacts arising from the above construction
activities are mainly associated with construction dust, construction noise,
waste management, ecology, land contamination and landscape and visual impact
issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.