Table 2 Main Construction Works carried out in the Reporting Period
|
January 2026 |
February 2026 |
March 2026 |
|
Contract
DC/2019/10: ·
Fixing GRC panel and CLP Substation ·
ELS Works and Pipe works for Modification of
Existing Inspection Chamber and Inlet Effluent Pipes from NSWSPS ·
T&C Works at IW ·
RC, ABWF and E&M works at IW (Remaining area) ·
RC, ABWF and E&M works at PST Stage 2 ·
ELS work and RC work at SDB ·
Predrill works and ELS work at ADB ·
External works at site-wide include water meter cabinet ·
RC structure at AGS ·
RC structure at TTS ·
ABWF and E&M work at STB ·
RC and E&M work at H2S ·
ELS work at UC3 ·
RC structure at Sludge Digester no. 1-3 with PP1 ·
ELS work at Sludge Digester no. 4-6 ·
RC work at Biogas Holder no. 2-3 foundation ·
Disposal of construction waste as indicated in Appendix F. Contract
DE/2020/1: ·
Installation of PV panels ·
Disposal of construction waste as indicated in Appendix F. |
Contract
DC/2019/10: ·
Fixing GRC panel at CLP Substation ·
ELS Works and Pipe works for Modification of
Existing Inspection Chamber and Inlet Effluent Pipes from NSWSPS ·
ABWF and T&C Works at IW ·
ELS works at PST Stage 2 ·
RC works at PST Stage 2 ·
RC works at SDB ·
ELS works at ADB and Underpass ·
RC works at AGS ·
RC structure at TTS ·
AWBF and E&M works at STB ·
ELS work at Sludge Digester no. 4-6 and UC4 ·
E&M work at Sludge Digester no. 1-3 ·
T&C work at Biogas Holder no.1 ·
Disposal of construction waste as indicated in Appendix F. Contract
DE/2020/1: ·
Installation of PV panels ·
Disposal of construction waste as indicated in Appendix F. |
Contract
DC/2019/10: ·
Fixing GRC panel and CLP Substation ·
Construction of Existing Inspection Chamber and Inlet Effluent
Pipes from Nam Sang Wai Sewage Pumping Station ·
ABWF and T&C Works at IW ·
ELS works at PST Stage 2 ·
RC works at SDB ·
ELS works at ADB and Underpass ·
RC works at AGS ·
RC structure at TTS ·
ABWF and E&M works at STB ·
ELS work at Sludge Digester no. 4 -6 and UC4 ·
E&M wok at Sludge Digester no. 1-3 ·
Water test and rectification work at Sludge Digester no. 1-3 ·
T&C work at Biogas Holder no.2 ·
Disposal of construction waste as indicated in Appendix F. Contract
DE/2020/1: ·
No site works in March ·
Disposal of construction waste as indicated in Appendix F. |