11                  FUTURE KEY ISSUES

11.1             Construction Programme for the Next Three Months

Contract DC/2019/10:

·     Fixing GRC panel at CLP Substation

·      Pipe works for Modification of Existing Inspection Chamber and Inlet Effluent Pipes from Nam Sang Wai Sewage Pumping Station

·     Temporary Road Works at IW (South Side) for FS Inspection’

·     ABWF and E&M works at IW (Remaining area)

·     ELS and RC works at PST Stage 2

·     RC work at SDB

·      ELS work at Underpass

·     Driven H-Pile works at ADB

·     External UU works at site-wide

·     RC structure at AGS and Water Tightness Test

·     RC structure at TTS and Water Tightness Test

·     ABWF, E&M and T&C work at STB

·     ELS work at UC2 and UC3

·     E&M, Water Tightness Test and Lining work at Sludge Digester no. 1-3

·     RC work at PP1

·     ELS work at Sludge Digester no. 4-6 and UC4

·      E&M work at Biogas Holder no. 2

Contract DE/2020/01:

·     Installation of PV panels and earth mat

11.2             Key Issues for the Coming Month

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3             Monitoring Schedules for the next three months

The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.