According to the EM&A Manual, a Landscape Architect or related
professional shall be employed to audit the implementation of landscape
construction works particularly during site clearance operations when the
proposed tree felling and transplanting will take place and subsequent
maintenance operations. Site audits should be undertaken every week during the
construction phase to check that the proposed landscape and visual mitigation
measures are properly implemented and maintained as per their intended objectives.
The mitigation measure recommended in the EIA Report as the audit requirements
for landscape and visual, including: preservation of existing vegetation,
transplanting of affected trees, compensatory tree planting, control of
night-time lighting glare, erection of decorative screen hoarding and
management of construction activities and facilities are summarized in Appendix J.
To monitor and audit the
implementation of landscape and visual mitigation measures for Contract
DC/2019/10, 4 weekly landscape and
visual site audits were carried out on 4, 10, 18 and 25 March 2026.
For Contract DE/2020/01, 1 site audit was carried on 12 March
2026 and there is
no landscape or visual impact for the indoor works under Contract DE/2020/01
No outstanding issues were
reported during the reporting month. The ET Leader’s Site Environmental Audit are
summarized in Appendix
M.