8.1.1
Site audits were carried out by ET on weekly basis at least once per
week to monitor the implementation of proper environmental management practices
and mitigation measures in the Project site
8.1.2
In the reporting month, four site inspections for
Contract DC/2019/10 were carried out on 4, 10, 18 and 25 March 2026.
8.1.3
In the reporting month, one site inspection for Contract DE/2020/01 was
carried out on 12 March 2026.
8.1.4
No outstanding issues were reported during the reporting month. The ET
Leader’s Site Environmental Audit are
summarized in Appendix M.
8.2
Advice on the Solid and Liquid Waste Management
Status
8.2.1
The Contractors registered as a chemical waste producer for the
Contract. Sufficient numbers of receptacles were
available for general refuse collection and sorting.
8.2.2
The management of waste generated by the construction is presented in Table 27.
8.2.3
The monthly summary of waste flow table is detailed in Appendix I.
8.2.4
If off-site disposal is required, the excavated marine mud from the
land-based works shall be disposed of at the designated disposal sites within
Hong Kong as allocated by the Marine Fill Committee or other locations as
agreed by the Director. The Contractor shall ensure no spilling and overflowing
of materials during loading / unloading / transportation is allowed.
8.2.5
The
Contractors was reminded that chemical waste should be properly handled
temporarily in designated chemical waste storage area on site in accordance
with the Code of Practice on the Packing, Labelling and Storage of Chemical
Waste.