Table 28 Status
of submissions required under the EP
|
EP Condition (EP-565/2019/A) |
Submission Title |
Submission Status |
|
Condition
2.9 |
Construction
Phase Emergency Response Plan |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.11 |
Pre-construction Ardeid Night Roost Survey Report |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
EM&A
Manual Sec. 7.3.3 & 7.3.4 |
Baseline
Bird Survey Report |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.12 |
Noise Mitigation Measures Plan |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
2.13 |
Proposal
for Minimization of Overspill Light to Ecological Sensitive Areas |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.14 |
Supplementary Contamination Assessment Plan |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
2.14 |
Contamination
Assessment Report for Main Storeroom & Workshops |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.14 |
Contamination Assessment Report for Mechanical
Workshop |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
2.14 |
Contamination
Assessment Report for Waste Storage Area |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.14 |
Contamination Assessment Report for SAS Thickener
House-1 |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
2.14 |
Contamination
Assessment Report for SAS Thickener House-2 |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 2.14 |
Contamination Assessment Report for Screening
Press House |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
2.15 |
Landscape
and Visual Mitigation Plan |
Submitted
to EPD with ET certification and IEC verification, to be finalised and made
available for public inspection via the dedicated website. |
|
Condition 3.3 |
Baseline Monitoring Report |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
3.4 |
Monthly
EM&A Report (from April 2021 to February 2026) |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |
|
Condition 3.5 |
Quarterly EM&A Report (from April 2021 to December 2025) |
Submitted to
EPD with ET certification and IEC verification, finalised and available for
public inspection via the dedicated website. |
|
Condition
4.2 |
Environmental
Monitoring Data from April 2021 to February 2026 |
Submitted
to EPD with ET certification and IEC verification, finalised and available
for public inspection via the dedicated website. |