11.1
Construction
Programme for the Next Three Months
· Fixing GRC panel at CLP Substation
· Pipe
works for Modification of Existing Inspection Chamber and Inlet Effluent Pipes
from Nam Sang Wai Sewage Pumping Station
· ABWF
and E&M works at IW (Remaining area)
· RC
works at PST Stage 2
· RC
work at SDB
· RC
work at Underpass
· RC
work at ADB
· External
UU works at site-wide
· RC
structure at AGS and Water Tightness Test
· RC
structure at TTS and Water Tightness Test and AWBF Works
· ABWF, E&M
and T&C work at STB
· ELS
work at UC2 and UC3
· E&M, Water
Tightness Test and Lining work at Sludge Digester no. 1-3
· RC work
at PP1
· ELS work
at Sludge Digester no. 4-6 and UC4
· E&M
work at Biogas Holder no. 2 & 3
Contract DE/2020/01:
· Installation of PV panels
11.2
Key Issues
for the Coming Month
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land contamination
and landscape and visual impact issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.