11.1
Construction
Programme for the Next Three Months
· Fixing GRC panel at CLP Substation
· Pipe works for Modification of Existing Inspection
Chamber and Inlet Effluent Pipes from Nam Sang Wai Sewage Pumping Station
· ABWF and E&M works at IW (Remaining area)
· RC works at PST Stage 2
· RC work at SDB
· RC work at Underpass
· RC work at ADB
· External UU works at site-wide
· RC structure at AGS and Water Tightness Test
· RC structure at TTS and Water Tightness Test and
AWBF Works
· ABWF, E&M and T&C work at STB
· ELS work at UC2 and UC3
· E&M, Water Tightness Test and Lining work
at Sludge Digester no. 1-3
· RC work at PP1
· ELS work at Sludge Digester no. 4-6 and
UC4
· E&M work at Biogas Holder no. 2 & 3
· Demolition of existing
consolidation tank at Zone 3
Contract
DE/2020/01:
·
Installation of PV
panels
11.2
Key Issues
for the Coming Month
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3
Monitoring
Schedules for the next three months
The tentative schedule for environmental monitoring in the next three
months is provided in Appendix E.