11.1 Construction
Programme for the Next Three Month
·
Ground investigation at SDB, AGS & TTS;
·
Ground investigation and footing construction
works at Walkway (Portion 5);
·
Driven pile works at STB (17nos.) & UC
(24nos.):
·
ABWF work
and fixing GRC panel at CLP Substation;
·
ELS work
and RC structure at IW & PST;
·
Installation of 813mm pipe pile at North and
West of AGS;
·
Installation of King
Post at AGS;
·
Erection
temp. loading platform at AGS;
·
ELS work at
AGS;
·
Installation of Sheet
pile at TTS;
·
Installation
of King post at TTS;
·
Erection
temp. loading platform at TTS;
·
ELS work at
TTS;
·
Installation of sheet
pile at STB;
·
ELS work at
STB;
·
Sheet piling
work around Sludge digester no. 1 – 3;
·
ELS work at
Sludge Digester no. 1-3;
·
Installation of sheet
pile at Biogas Holder no. 1;
·
ELS work at
Biogas Holder no. 1;
·
ELS and
construction of UC no.5;
·
Demolition of
underground structure at A. tank no. 5-8;
·
Construction of temp.
haul road in front of central Control Room:
·
Demolition of
underground structure at pump room of AFT; and
·
Demolition of Mixed
Liquor Distribution & Sludge Draw-off Chamber at FST no. 5-8.
11.2 Key Issues for the Coming Month
11.2.1 Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3 Monitoring
Schedules for the next three months
11.3.1 The tentative schedule
for environmental monitoring in the next three months is provided in Appendix
E.