This Monthly Environmental
Monitoring and Audit (EM&A) Report is prepared for Contract No. SPW 02/2023
“Environmental Team for Construction of Yuen Long Effluent Polishing Plant
Stage 1”. Drainage Services Department (DSD) has appointed Aurecon Hong Kong
Limited (Aurecon) to undertake the Environmental Team services for the project
and implement the EM&A works.
This is the 28th
Monthly EM&A Report for the construction phase which summaries findings of
the EM&A programme during the reporting period from 1 July 2023 to 31 July
2023. As informed by the Contractor, major activities in the reporting month
were:
· Ground investigation at SDB
& TTS
· Laying cable ducts and
construction of cable draw pits near entrance of YLSTW
· ABWF and E&M works at CLP
substation
· ELS works and RC structure
works at IW & PST
· Installation of 813mm pipe
pile at North of AGS
· Installation of King Post
at AGS
· Breaking and removal of RAS
(below ground)
· Installation of observation
wells and dewatering well at AGS
· Demolition of Mixed Liquor
Distribution & sludge Draw-off Chamber at FST no. 5-8
· Installation of sheet pile
at TTS
· Installation of King post
at TTS
· Installation of observation
wells and dewatering well at TTS
· Installation of sheet pile
at STB
· Demolition of underground
structure at pump room of AFT
· Installation of sheet pile
at UC5
· ELS works at UC5
· Sheet piling installation
around Sludge digester no. 1 – 3
· Installation of sheet pile
at Biogas Holder no. 1
· Construction of temporary
200m3 sludge holding tanks, and
· Disposal of construction
waste as indicated in Appendix I.
Breaches of Environmental Quality Performance
Limits (AL levels)
No Action and Limit Level exceedance was
recorded for air quality monitoring and construction noise monitoring in the
reporting month.
No Action and Limit Level exceedance was
recorded for water quality monitoring in the reporting month.
No Action / Limit exceedance was recorded for
noise levels at stations (NMS1 and NMS2) in close proximity to the two active
ardeid night roosts (ANR1 and ANR2) observed within the Survey Area during the
reporting month.
No Action / Limit exceedance for the
ecological monitoring of birds in the reporting month.
No corrective actions were required according
to the Event and Action Plans for the Monitoring Parameters.
Land Contamination
Regular site inspection was
carried out to ensure the recommended mitigation measures are properly
implemented. The signed final Contamination Assessment Report (CAR) for “Main
Storeroom & Workshops”, “Mechanical Workshop”, “Waste Storage Area”, “SAS
Thickener House-1” and “SAS Thickener House-2” were submitted to EPD
respectively on 1st November 2021, 23rd November 2021, 29th April 2022, 6th
July 2022 and 19th June 2023. No contaminated soil and ground water was found
within the Main Storeroom & Workshop, Mechanical Workshop, Waste Storage
Area, SAS Thickener House-1 and SAS Thickener House-2, and no remedial action
is required for these locations.
Complaint Log
No complaints were received
in the reporting period.
Notifications of Summons and Successful Prosecutions
No notifications of summons
and successful prosecutions were received in the reporting period.
Reporting Change
There were no reporting
changes during the reporting month.
Future Key Issues
The main works will be
anticipated in the next three months are as follow:
· Ground investigation at SDB, AGS & TTS.
· Ground investigation and footing construction works at Walkway (Portion
5)
· ABWF work and fixing GRC panel at CLP Substation
· ELS work and RC structure at IW & PST
· Installation of King Post at AGS
· Installation of 813mm pipe pile at North near West of AGS
· Installation of observation wells and dewatering well at AGS
· Erection temp. loading platform at AGS
· ELS work at AGS
· Demolition of underground structure at A. tank no. 5-8
· Installation of Sheet pile at TTS
· Installation of King post at TTS
· Installation of observation wells and dewatering well at TTS
· Erection temp. loading platform at TTS
· ELS work at TTS
· Demolition of Mixed Liquor Distribution & sludge Draw-off Chamber at
FST no. 5-8
· Demolition of underground structure at pump room of AFT
· Driven pile works at STB (17nos.)
· Installation of sheet pile at STB
· ELS work at STB
· Installation of observation wells and dewatering well at STB
· ELS and construction of UC no.5
· Sheet piling work around Sludge digester no. 1-3
· ELS work at Sludge Digester no. 1-3
· Installation of observation wells and dewatering well at Sludge Digester
no. 1-3
· Installation of sheet pile at Biogas Holder no. 1
· ELS work at Biogas Holder no. 1
· Driven pile works at UC (24nos.) near SDB
· Construction of temp. haul road in front of central Control Room