11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·             Demolition of Admin. Building;

·             Ground investigation at SDB & Biogas Holder;

·             Excavation of trench for laying power cables and cable draw pits near entrance of YLSTP;

·             ABWF work and fixing GRC panel at CLP Substation;

·             ELS work and RC structure at IW & PST;

·             Installation of 813mm pipe pile at North and West of AGS;

·             Installation of King Post at AGS;

·             Erection temp. loading platform at AGS;

·             ELS work at AGS;

·             Installation of Sheet pile at TTS;

·             Installation of King post at TTS;

·             ELS work at TTS;

·             Installation of sheet pile at STB;

·             ELS work at STB;

·             ELS work at SD;

·             Sheet piling work around Sludge digester no. 1 – 3;

·             ELS work at Sludge Digester no. 1-3;

·             Removal of concrete blocks and filled soil at Biogas Holder no. 1; and

·             Installation of sheet pile and ELS for construction of UC no.5.

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the next three months

11.3.1     The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.