11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·        Ground investigation at SDB;

·        Excavation of trench for laying power cables and cable draw pits near entrance of YLSTP;

·        ABWF work and fixing GRC panel at CLP Substation;

·        ELS work and RC structure at IW & PST;

·        Laying 1200mm outfall pipe for temp. diversion;

·        Installation of 813mm pipe pile at North and West of AGS;

·        Installation of King Post at AGS;

·        Erection temp. loading platform at AGS;

·        Breaking and removal of RAS (below ground);

·        ELS work at AGS;

·        Installation of Sheet pile at TTS;

·        Installation of King post at TTS;

·        Erection temp. loading platform at TTS;

·        ELS work at TTS;

·        Installation of sheet pile at STB;

·        ELS work at STB;

·        Sheet piling work around Sludge digester no. 1 – 3;

·        ELS work at Sludge Digester no. 1-3;

·        Removal of surcharge including concrete blocks and filled soil at Biogas Holder no. 1;

·        Installation of sheet pile at Biogas Holder no. 1;

·        ELS work at Biogas Holder no. 1; and

·        Installation of sheet pile, ELS and construction of UC no.5.

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the next three months

11.3.1     The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.