11.1 Construction
Programme for the Next Three Month
·
Demolition of Admin. Building and
RAS by silent method;
·
Ground investigation at UC, SDB, SDT & STB;
·
Excavation of temp.
trench for laying power cables and cable draw pits near YLSTP’s entrance;
·
Construction
of CLP Substation;
·
ELS work and RC structure at IW & PST;
·
Installation of 813mm
pipe pile at North, West and East of AGS;
·
Installation of King
Post at AGS;
·
Erection
temp. loading platform at AGS;
·
ELS work
at AGS;
·
Installation of Sheet
pile at TTS;
·
Installation of King
post at TTS;
·
ELS work at
TTS;
·
Installation of sheet
pile at STB;
·
ELS work at
STB;
·
Environmental Drill
Holes at AFT;
·
Sheet piling
work around Sludge digester no. 1 – 3;
·
ELS work at
Sludge Digester no. 1-3; and
·
Installation of
concrete blocks and filling soil Surcharge at Biogas Holder no. 1.
11.2 Key Issues for the Coming Month
11.2.1 Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, waste management, ecology, land
contamination and landscape and visual impact issues.
11.3 Monitoring
Schedules for the next three months
11.3.1 The tentative schedule
for environmental monitoring in the next three months is provided in Appendix
E.