11.     FUTURE KEY ISSUES

11.1       Construction Programme for the Next Three Month

·             Demolition of Admin. Building and RAS by silent method;

·             Ground investigation at UC, SDB, SDT & STB;

·             Excavation of temp. trench for laying power cables and cable draw pits near YLSTP’s entrance;

·             Construction of CLP Substation;

·             ELS work and RC structure at IW & PST;

·             Installation of 813mm pipe pile at North, West and East of AGS;

·             Installation of King Post at AGS;

·             Erection temp. loading platform at AGS;

·             ELS work at AGS;

·             Installation of Sheet pile at TTS;

·             Installation of King post at TTS;

·             ELS work at TTS;

·             Installation of sheet pile at STB;

·             ELS work at STB;

·             Environmental Drill Holes at AFT;

·             Sheet piling work around Sludge digester no. 1 – 3;

·             ELS work at Sludge Digester no. 1-3; and

·             Installation of concrete blocks and filling soil Surcharge at Biogas Holder no. 1.

11.2      Key Issues for the Coming Month

11.2.1     Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, waste management, ecology, land contamination and landscape and visual impact issues.

11.3      Monitoring Schedules for the next three months

11.3.1     The tentative schedule for environmental monitoring in the next three months is provided in Appendix E.